Difference between revisions of "Run Coordinator report: Summer 2020 w5"
From GlueXWiki
(2 intermediate revisions by the same user not shown) | |||
Line 1: | Line 1: | ||
RC summary, 08/27/2020 - 09/02/2020, Igal Jaegle | RC summary, 08/27/2020 - 09/02/2020, Igal Jaegle | ||
− | During the first 4 days, we were in data production more and | + | During the first 4 days, we were in data production more, and the last 3 days were devoted to CPP tests & DIRC commissioning. |
The downtime due to us was large: 38.8hr | The downtime due to us was large: 38.8hr | ||
*12hr hall access for installing the CPP test | *12hr hall access for installing the CPP test | ||
Line 8: | Line 8: | ||
The most notable issues were | The most notable issues were | ||
*CDC & FDC HV did trip without any alarms resulting in the loss of 3 data production runs | *CDC & FDC HV did trip without any alarms resulting in the loss of 3 data production runs | ||
− | *DIRC problems which required invasive hall access | + | *DIRC problems (South Box Group 9 LV) which required invasive hall access |
*Solenoid did not ramp down and up as expected delaying the TRD-GEM installation by 5 hours | *Solenoid did not ramp down and up as expected delaying the TRD-GEM installation by 5 hours | ||
− | + | *Beam down due to weather + communication wrath during 18hr | |
+ | Apart from that, in total 18B "good" physics trigger were taken. |
Latest revision as of 20:22, 12 September 2020
RC summary, 08/27/2020 - 09/02/2020, Igal Jaegle
During the first 4 days, we were in data production more, and the last 3 days were devoted to CPP tests & DIRC commissioning. The downtime due to us was large: 38.8hr
- 12hr hall access for installing the CPP test
- 14hr hall access for de-installing the CPP test and installing TRD-GEM
- 12.8hr invasive hall access for detector (DIRC) repair, active collimator scan, changing radiator, and starting runs
The most notable issues were
- CDC & FDC HV did trip without any alarms resulting in the loss of 3 data production runs
- DIRC problems (South Box Group 9 LV) which required invasive hall access
- Solenoid did not ramp down and up as expected delaying the TRD-GEM installation by 5 hours
- Beam down due to weather + communication wrath during 18hr
Apart from that, in total 18B "good" physics trigger were taken.