+ | * Discussed schedule, May happen as early as Mid August | ||
+ | *Elton added empty target runs to plan | ||
+ | * Test will start with 1 sheet of lead | ||
+ | * Need to speak with Eugene about procurement priorities | ||
+ | * Reviewd 3D models | ||
* Set up new meeting in 2 weeks | * Set up new meeting in 2 weeks |
Latest revision as of 06:59, 24 July 2020
Meeting Time and Place
Thursday July 23, 2020, 1:30pm Bluejeans https://bluejeans.com/735541157/3638?src=calendarLink
- Present - Elton, Dave, Stephanie, Bobby, Ilya, Rory
Agenda
- Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/July_09,_2020_CPP_Design_Meeting
- Upcoming run, possible testschedule Media:CPP_Tests_Aug2020.pdf
- CPP Test 2020 - Schedule
- Test Layout 3D model
- Design/Procurement status
- Things to work out
- Gas line manifold
- Adjustable lead absorber
- Alignment hardware
- Complete structural analysis
- Develop Detailed installation plan
- Develop Design/operational/Maintenance Requirements
Minutes and Action Items
- Reviewed minutes of last meeting
- Discussed schedule, May happen as early as Mid August
- Elton added empty target runs to plan
- Test will start with 1 sheet of lead
- Need to speak with Eugene about procurement priorities
- Reviewd 3D models
- Set up new meeting in 2 weeks