Difference between revisions of "OWG meeting 5-Sep-2008"
m |
m |
||
(8 intermediate revisions by the same user not shown) | |||
Line 3: | Line 3: | ||
* Announcements | * Announcements | ||
* Review of minutes from [[OWG meeting 22-Aug-2008 | 22-Aug-2008]] meeting | * Review of minutes from [[OWG meeting 22-Aug-2008 | 22-Aug-2008]] meeting | ||
− | * | + | * [[Media:Online-Graham-5-Sep-2008.ppt|DAQ update]] - Graham |
+ | * Collaboration meeting - [http://www.jlab.org/Hall-D/software/wiki/index.php/GlueX-Collaboration-Sept-2008 agenda], preparation - All | ||
* Update on fiber test stand - Beni | * Update on fiber test stand - Beni | ||
− | * | + | * Trigger hardware development - Dave D, Fernando, or Chris |
− | + | * Electronics update - Fernando, Chris, Ben, Ed, etc. | |
− | * Electronics update - | + | |
Line 22: | Line 23: | ||
'''No meeting 19-Sep-2008 due to GlueX Collaboration meeting''' | '''No meeting 19-Sep-2008 due to GlueX Collaboration meeting''' | ||
− | + | Fri 3-Oct-2008 2pm CC F326 | |
Line 29: | Line 30: | ||
=Minutes= | =Minutes= | ||
+ | |||
+ | Attendees: Elliott W, Graham H, Simon T, Dave D, Elton S, David L, Mark I, Alex S, Dave A, Carl T, Vardan G, Beni Z, Jim S. | ||
+ | |||
+ | |||
+ | '''DAQ Status''' | ||
+ | |||
+ | Graham gave an overview of recent progress in the DAQ group. See his talk for numerous details. | ||
+ | |||
+ | * EMU prototype done, now being tested. | ||
+ | * Uses Java and C (native methods). | ||
+ | * EMU<->EMU communications tested, easily saturates GB Ethernet bandwidth with low CPU usage. | ||
+ | * Estimate need seven DAQ staff members to complete CODA3, have five now. Two more approved but not funded. | ||
+ | * Completion dates will slip if staff members not hired. | ||
+ | |||
+ | |||
+ | '''Collaboration Meeting Agenda''' | ||
+ | |||
+ | Agenda include talks on electronics by Fernando, trigger by Dave D, and DAQ/controls by Elliott (given by Dave L, as Elliott will be out of town). | ||
+ | |||
+ | |||
+ | '''Fiber Test Stand''' | ||
+ | |||
+ | Beni reported he is taking data with no problems. Dark box materials still have not arrived. It takes 5-6 hours to test one fiber. | ||
+ | |||
+ | |||
+ | '''Trigger Status''' | ||
+ | |||
+ | Dave D noted that the CTP and SD are coming along, the TI prototype is working. Expect contracts for boards by the end of FY 08. | ||
+ | |||
+ | |||
+ | '''Electronics''' | ||
+ | |||
+ | Dave A reported: | ||
+ | |||
+ | * Mini-SD board coming, uses front panel connectors. | ||
+ | * PCI-based TI prototype working at basic level, more testing and development needed. |
Latest revision as of 14:07, 10 September 2008
Contents
Agenda
- Announcements
- Review of minutes from 22-Aug-2008 meeting
- DAQ update - Graham
- Collaboration meeting - agenda, preparation - All
- Update on fiber test stand - Beni
- Trigger hardware development - Dave D, Fernando, or Chris
- Electronics update - Fernando, Chris, Ben, Ed, etc.
Time/Location
5-Sep-2008 2pm CC F326
Announcements
Next Meeting
No meeting 19-Sep-2008 due to GlueX Collaboration meeting
Fri 3-Oct-2008 2pm CC F326
New Action Items from this Meeting
Minutes
Attendees: Elliott W, Graham H, Simon T, Dave D, Elton S, David L, Mark I, Alex S, Dave A, Carl T, Vardan G, Beni Z, Jim S.
DAQ Status
Graham gave an overview of recent progress in the DAQ group. See his talk for numerous details.
- EMU prototype done, now being tested.
- Uses Java and C (native methods).
- EMU<->EMU communications tested, easily saturates GB Ethernet bandwidth with low CPU usage.
- Estimate need seven DAQ staff members to complete CODA3, have five now. Two more approved but not funded.
- Completion dates will slip if staff members not hired.
Collaboration Meeting Agenda
Agenda include talks on electronics by Fernando, trigger by Dave D, and DAQ/controls by Elliott (given by Dave L, as Elliott will be out of town).
Fiber Test Stand
Beni reported he is taking data with no problems. Dark box materials still have not arrived. It takes 5-6 hours to test one fiber.
Trigger Status
Dave D noted that the CTP and SD are coming along, the TI prototype is working. Expect contracts for boards by the end of FY 08.
Electronics
Dave A reported:
- Mini-SD board coming, uses front panel connectors.