Difference between revisions of "Aug 18, 2008 Calorimetry"
From GlueXWiki
(→Reference Documents) |
(→Agenda) |
||
Line 25: | Line 25: | ||
# Discussion | # Discussion | ||
+ | #* Preparation for construction procurements in FY09 | ||
#* Geometry and drawings - sign off procedures | #* Geometry and drawings - sign off procedures | ||
#* Schedule for evaluation of bid responses to fiber RFP. | #* Schedule for evaluation of bid responses to fiber RFP. |
Revision as of 10:18, 14 August 2008
Connection
- The meeting will be held at 10:30 am ET
- Phone:
- +1-800-377-8846 : US
- +1-888-276-7715 : Canada
- +1-302-709-8424 : International
- then enter participant code: 39527048# (remember the "#")
Reference Documents
- Previous minutes: July 21, 2008 Calorimetry
- Schedule, Tracker and Drawings (gluex pass)
To-do List from previous meeting
- Identify files with new geometry (Beni)
- Estimates of pedestal width (electronic noise, etc.) for FM PMTs. The dark rate should be negligigle in this case.
- Resolution studies with up-to-date geometry (Blake)
- Resolution studies with different segmentation for the outer section.
- Add F100 rad hard glass to simulation.
- Calibration meeting Tues Aug 26
- Decision on Bcal sampling fraction needed by Sep.
Agenda
- Discussion
- Preparation for construction procurements in FY09
- Geometry and drawings - sign off procedures
- Schedule for evaluation of bid responses to fiber RFP.
- Discussion on agenda Items for collaboration meeting
- Reports
- Geometry for simulations in repository (Beni)
- Updates on simulation of performance (Blake)
- Preparations for construction (George and Jim)
- Measurements of fiber light output (Andrei)
- Preparations for fiber testing at JLab (Beni)
- Review of To-do List
- Updates
- Calibration system
- FCAL
- BCAL
- Any other business
Minutes
Attending: