Difference between revisions of "Run Planning Meeting Notes, Sep 12-19, 2018"
From GlueXWiki
Line 5: | Line 5: | ||
* [https://calendar.google.com/calendar/embed?src=halldops%40gmail.com&ctz=America%2FNew_York Run Plan Google Calendar] | * [https://calendar.google.com/calendar/embed?src=halldops%40gmail.com&ctz=America%2FNew_York Run Plan Google Calendar] | ||
* [https://calendar.google.com/calendar/embed?src=503o985nbesua43smquc510o8k%40group.calendar.google.com&ctz=America%2FNew_York Accel. Plan Google Calendar] | * [https://calendar.google.com/calendar/embed?src=503o985nbesua43smquc510o8k%40group.calendar.google.com&ctz=America%2FNew_York Accel. Plan Google Calendar] | ||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
== Wednesday, Sep 19 at 08:45 == | == Wednesday, Sep 19 at 08:45 == |
Latest revision as of 06:52, 20 September 2018
<- Back to Run Coordination Meetings:Fall2018 Run
Wednesday, Sep 19 at 08:45
- Notes from the previous 24 hours:
- CEBAF:
- Previously observed obstruction in NL is gone, probably nitrogen ice
- Beam at 5R
- CW for Hall C on Thursday, other halls Friday swing
- Action Items:
- Hot Check OUT Status 8% ready ; 1% checked ; 91% not ready
- Issues
- Reports:
- Run Plan
- AOB
Tuesday, Sep 18 at 08:45
- Notes from the previous 24 hours:
- CEBAF:
- NL is up, obstruction/aperture tests today
- SL will be brought up today
- Action Items:
- Hot Check OUT Status 0% ready ; 1% checked ; 99% not ready
- Issues
- Reports:
- Run Plan
- AOB