# Announcements | # Announcements | ||
# Status of the CUA construction contract - ''Franz'' | # Status of the CUA construction contract - ''Franz'' | ||
− | # [ | + | # [https://halldweb.jlab.org/doc-private/DocDB/ShowDocument?docid=2181 Status of the microscope construction contract] - ''James'' |
# Status of the microscope electronics construction - ''Alex'' | # Status of the microscope electronics construction - ''Alex'' | ||
# Progress with pair spectrometer hodoscope - ''Sascha'' | # Progress with pair spectrometer hodoscope - ''Sascha'' |
Latest revision as of 16:48, 24 February 2017
Organization
- Time: 11:30 EST
- Place: ESNET and Seevogh (Jlab community)
- Connecting: instructions are here
- Present: Richard J., Alex B., James M., Brendan P., Curtis M., Mike M., Yi Q., Hovanes E., Sascha S., Tim W., Dan S., Franz K., and Barry R.
Agenda
- Announcements
- Status of the CUA construction contract - Franz
- Status of the microscope construction contract - James
- Status of the microscope electronics construction - Alex
- Progress with pair spectrometer hodoscope - Sascha
- Discussion of installation issues - Richard
- pair converter target design
- diamond radiator target holder
- active collimator software interface
- microscope readout radiation shielding
- low-voltage power supplies and interfaces
- Tagger magnet mapping plan - Tim
- Update on polarimetry - Mike
- State of the beamline simulation - Sascha
- any other business