Difference between revisions of "Run Coordination Meetings: Spring 2017 Run"

From GlueXWiki
Jump to: navigation, search
(Hot Checkout)
(Readiness for Fall 16 run)
Line 199: Line 199:
  
 
==Readiness for Fall 16 run ==
 
==Readiness for Fall 16 run ==
*<Solenoid (Eugene/Beni) is Ready.
+
*Solenoid (Eugene/Beni)  
**<strike>Check with Spring16 data that running at 1350A vs 1200A is beneficial (Paul Mattione/Mike/Alex)</strike> Running at 1350A is prefereable for GlueX.
+
** <strike>Will ramp to 100 A a few days before the start of the run, then leave power supply on at 0 V until experiment. Done. </strike>
+
  
 
*Surveys (Tim/Tom)
 
*Surveys (Tim/Tom)
**<strike>Target Fiducialization/alignment (Monday Sept. 19)</strike> Done
+
 
**<strike>Tagger Microscope alignment, Tagger Hodoscope Survey (Tuesday Sept 20)</strike> Done
+
**<strike>Start Counter Alignment, Target Cart Alignment (Thu. Sept 22)</strike> Done
+
**<strike>Primary Collimator Fiducialization/alignment, Beam Profiler Alignment (Fri Sept 23)</strike> Done
+
**<strike>CompCal Fiducialization/Alignment (Monday Sept 26)</strike> Done
+
** <strike>PS High Granularity Alignment, PS beamline alignment (Tuesday Sept 27)</strike> Done
+
** <strike>TAGH needs to be resurveyed.</strike>
+
** <strike>Goniometer fiducialization. </strike>
+
 
*DAQ  (Sergei)
 
*DAQ  (Sergei)
**<strike>Waiting on Trigger to be ready.</strike>
+
 
** Most systems are tested. Successfully ran at 60 kHz, 99% livetime.
+
 
*Trigger (Alex S.)
 
*Trigger (Alex S.)
**System is robust. Running on cosmics. Still a few problems to be addressed:
+
 
***<strike>FDC F125 send error messages.</strike> Fixed
+
***<strike>F250 DAC sometimes fails.</strike> Fixed
+
***Problem with PS/Start Counter crate: TDC sometimes generates readout problem. Problem seems to now be gone but need to be checked.
+
***<strike>Problem with TagM. TDC crate. </strike> Fixed now.
+
 
*Beam line  
 
*Beam line  
**<strike>Diamond status.</strike>
+
**Diamond status.
*** <strike>3 new and characterized diamonds are now JLab.</strike>
+
 
**Tagger hodoscope (Nathan/Franz)
 
**Tagger hodoscope (Nathan/Franz)
***<strike> Remove protective plastic tubes. Franz to remove part of them this week (Sept. 19-23).</strike> Done on 19th.
+
**Tagger microscope (Alex B./Richard)
***<strike>Once tubes are removed, need to check for light leak with scalers.</strike> Done.
+
***New fiber installation
***<strike> Needs to be resurveyed</strike>
+
*** <strike> Needs testing with DAQ<strike>
+
** <strike>Tagger microscope (Alex B./Richard)</strike> TAGM is ready
+
***<strike>waiting for survey to be completed before doing hot check out.</strike> Done
+
***<strike>Need to put back shielding.</strike>
+
***<strike>1 MPOD to power preamp errors out, Alex B following up. Blower on and shroud covered, ready for dark rate testing.</strike>
+
 
**Goniometer (Hovanes)
 
**Goniometer (Hovanes)
***<strike>Goniometer is back. Issue with control hardware. Need to be fixed and tested. </strike>
+
**Collimator, Active collimator, profiler, flux monitor (Alex B./Hovanes).   
*** <strike>To be fiducialized. Done.</strike>
+
**Collimator, <strike>Active collimator, profiler, flux monitor </strike>(Alex B./Hovanes).   
+
*** <strike>AC installed and wired, needs DAQ testing</strike> A.C. needs some fine tuning.
+
*** Flux monitor cabled (was this verified?)
+
***<strike>Collimator vertical motion control is done. 2D scan procedure is written.</strike>
+
***<strike>Profiler is ready.</strike>
+
 
**PS system (Alex S.)
 
**PS system (Alex S.)
***Need software for online monitoring of photon flux.
+
**Polarimeter (M. Dugger/Nathan)  
***<strike>Replace thermal pads?: Will decide this week (Sept. 19-23).</strike> No time to installed them for this run.
+
***<strike>Installed, alignment in progress</strike>
+
***<strike>High Granularity detector had Power Supply glitches. Now fixed.</strike>
+
***<strike>Needs DAQ testing</strike>
+
**<strike>Polarimeter (M. Dugger/Nathan) </strike> Polarimeter is ready
+
***<strike>Now under vacuum.</strike>
+
***<strike>Signals seen on all channels with source and scope.</strike>
+
***<strike>DAQ tested</strike>
+
 
**Target (Tim/Alexandre D.)
 
**Target (Tim/Alexandre D.)
***<strike>Ice test done. Leak fixed. Thin frost seen. Will add MLI to improve insulation. Leak fixed. </strike>
+
**TAC (Hovanes)
***<strike>Target is now inserted. </strike>
+
**<strike>TAC (Hovanes) TAC is ready and (re)checked. </strike>
+
 
**Slow control (Hovanes)
 
**Slow control (Hovanes)
***<strike>Goniometer motion.</strike>
 
***<strike>Need to work on vertical col. motion and need to program ComCal. (PrimEx detector) motion. </strike>
 
***<strike>Have implemented temperature thr. that shut down the crates. For now, they will operate between 62F<T<82F </strike>
 
 
**RF (Paul Mattione)
 
**RF (Paul Mattione)
***<strike>Fernando is implementing new TDC firmware for CAEN. </strike>
 
***<strike>New board is installed.</strike>
 
***<strike>Then, Paul to test the RF system.</strike>
 
 
**Radiation monitors
 
**Radiation monitors
***<strike>Need to move a photon probe near goniometer. Done</strike>
+
***Downstream photon probe is broken.  
***<strike>Install OSL and chromosticks<strike>
+
 
*Detector systems
 
*Detector systems
 
**ST (Mark Ito)
 
**ST (Mark Ito)
***<strike>Was test-cabled. Will be de-cabled, inserted and re-cabled.
 
***Inserted, powered up, working with stand alone DAQ.
 
***Crate burned 2 TI modules. Removed from main DAQ readout.</strike>
 
***ST is now re-installed and need to be rechecked..
 
 
**FDC (Lubomir)  
 
**FDC (Lubomir)  
***One sector doesn't hold HV (no change)
 
***Strange noise seen on each 3rd card of each chamber. Seen at 60 kHz but not at 1 kHz.
 
 
**CDC (Beni)
 
**CDC (Beni)
***<strike>Up and running
 
***Calibrated baselines, problems with 2 channels</strike>
 
***<strike>2 weekends of cosmic data desired. </strike>
 
 
** BCal (Elton)
 
** BCal (Elton)
***Was turned on on Sept. 14th. <strike> Turned on LED pulser too. One of the LED low voltage doesn't work. Chris is checking it.
 
***Stand alone DAQ run, all LV and SiPMs working. Intermittent problems with ADCs, possibly initialization.</strike>
 
***<strike>Checked data and saw that many channels are missing. TDC were missing. This is fixed now </strike>
 
 
** FCal (Adesh)
 
** FCal (Adesh)
***<strike>Was turned on this week (Sept. 19-23).</strike>. On since then.
 
*** Replaced 22 bases week of 19-24 Sept, more failures since at rate of 1-2 per day.
 
*** Keep replacing basis when needed.
 
***<strike>Adesh to do the HCO. Done</strike>
 
 
**TOF (Mark Ito/Beni/Alex. Ostrovidov)  
 
**TOF (Mark Ito/Beni/Alex. Ostrovidov)  
***<strike>Beni: was able to do a first calibration but unable to do it anymore. Replacing a HV module. </strike>
 
***<strike>Currently taking data for TDC correction tables.</strike>
 
*** Paul E. would like to install a lucite shield. Fitting it was tested and it fits fine.
 
*** Need to verify that all ADC channels are set-up correctly.
 
 
*Online monitoring (David L.)
 
*Online monitoring (David L.)
**<strike>Implemented Root 6
+
*Calibration/reconstruction/offline monitoring (Paul Mattione)
**Check compatibility with new F250 format. (One aspect of format might cahnge this week)
+
**Ready to go with occupancy and new higher level reconstruction histograms
+
**As ready as can be.</strike>
+
*<strike>Calibration/reconstruction/offline monitoring (Paul Mattione)</strike>
+
**Ready.
+
 
*Level 3 Trigger  (David L.)
 
*Level 3 Trigger  (David L.)
**<strike>As ready as can be given the uncertainty on what to do.</strike>
 
 
*Safety documents (Beni):
 
*Safety documents (Beni):
**<strike>ESAD must be updated to include safety procedure for ComCal. motion.</strike>
+
**ESAD must be updated to include safety procedure for ComCal. motion.
**<strike>ESAD ready, RSAD should be ready. </strike>
+
**ESAD ready, RSAD should be ready.  
 
*Hall Status/safety (Tom/Tim)
 
*Hall Status/safety (Tom/Tim)
 
**Ready
 
**Ready
 
*Other topics?
 
*Other topics?

Revision as of 20:06, 10 January 2017

Meeting General Agenda

Connect Information

To connect from the outside by phone please do the following

1.) To join via a Web Browser, go to the page [1] https://bluejeans.com/660743227.

2.) To join via Polycom room system go to the IP Address: 199.48.152.152 (bjn.vc) and enter the meeting ID: 660743227.

3.) To join via phone, use one of the following numbers and the Conference ID: 660743227.

4.) The moderator code is 8394

Dial Either +1 408 740 7256 or +1 888 240 2560 for US or Canada

Specific instructions for connecting from JLab's Hall D conference room:

  • Turn polycon on if necessary (do it before turning the computer on)
  • With the polycon, place a call at 199.48.152.152
  • Press # to enable the polycom keypad, then enter the meeting id: 660743227 and #
  • You may have to unmute the microphone: #*4
  • Turn the computer on if needed

Beam and Hall configuration

  • Beam energy expected: 11.632 GeV (include synchrotron radiation losses, except for the Hall D ramp).
  • Solenoid on at 1350A. Any field changes should be avoided if possible.
  • Beam current: CW 1 nA-1.5 μA. 250 MHz frequency.
  • FFB on or Position Slow Lock on (FFB doesn't operate below 50nA).
  • Radiators:
    • Goniometer diamond radiators:
      • J1a50       (50 μm - 4.1·10-4 R.L., 4×4 mm²) - old crystal - excellent rocking curve
      • JD70-100 (58 μm - 4.8·10-4 R.L., 7×7 mm²) - new crystal - excellent rocking curve
      • JD70-105 (47 μm - 3.9·10-4 R.L., 7×7 mm²) - new crystal - good rocking curve
      • JD70-104 (17 μm - 1.4·10-4 R.L., 7×7 mm²) - new crystal - wider rocking curve - marginally usable
    • We also have one 10 μm Al radiator.
    • Amorphous
      • 1.5 µm Al (1.7·10-5 R.L.)
      • 10 µm Al (11.2·10-5 R.L.)
      • 30 µm Al (33.7·10-5 R.L.)
  • Tagger quadrupole on (-4.2 A).
  • Collimator hole: Both 5 mm diameter and 3.4 mm diameter. Default running: 5.0 mm

General Information

This document describes the run plan for the Hall D Spring 2017 run.

  • Schedule for the Spring 2017 run:
  1. Jan. 26th-Jan. 29th: Electron beam restoration
  2. Jan. 30th-Mar. 22nd: Hall D Spring run.
  3. Every Tuesdays: 12h of beam study. Every Thursdays, if necessary: 8h of RF recovery.
  • Experiment: GlueX E12-06-102 Production
  • Planned tests:
    • High-intensity GlueX test (invasive, 3 shifts)
    • TPol low energy photon run (invasive, 2 shifts)
    • ComCAL(PrimeX) prototype test (parasitic)
  • Expected Staffing and responsibilities:
    • The Run Coordinator oversees the commissioning:
      • Thur. Jan. 26 - Sun. Jan. 29 (4 days): A. Deur (accelerator restoration)
      • Mon. Jan. 30 - Wed. Feb. 8 (10 days): A. Deur
      • Wed. Feb. 8 - Wed. Feb. 15 (7 days): M. Dalton (with Mon. 6th - Wed. 8th overlap)
      • Wed. Feb. 15 - Wed. Feb. 22 (7 days): A. Ostrovidov (with Mon. 13th - Wed. 15th overlap)
      • Wed. Feb. 22 - Wed. Mar. 1 (7 days): W. Boeglin (with Mon. 20th - Wed. 22nd overlap)
      • Wed. Mar. 1 - Wed. Mar. 8: (7 days): S. Dobbs (with Mon. 27th - Wed. 1st overlap)
      • Wed. Mar. 8 - Wed. Mar. 15: (7 days): R. Jones (with Mon. 6th - Wed. 8th overlap)
      • Wed. Mar. 15 - Wed. Mar. 22: (7 days): D. Lawrence (with Mon. 13th - Wed. 15th overlap)


Runplan

Hall D white board (current run plan)

Hall D counting room white board

Runplan time charts


Accelerator status

Hot Checkout

  1. Hot Check OUT Status 97% ready ; 2% checked ; 1% not ready

Readiness for Fall 16 run

  • Solenoid (Eugene/Beni)
  • Surveys (Tim/Tom)
  • DAQ (Sergei)
  • Trigger (Alex S.)
  • Beam line
    • Diamond status.
    • Tagger hodoscope (Nathan/Franz)
    • Tagger microscope (Alex B./Richard)
      • New fiber installation
    • Goniometer (Hovanes)
    • Collimator, Active collimator, profiler, flux monitor (Alex B./Hovanes).
    • PS system (Alex S.)
    • Polarimeter (M. Dugger/Nathan)
    • Target (Tim/Alexandre D.)
    • TAC (Hovanes)
    • Slow control (Hovanes)
    • RF (Paul Mattione)
    • Radiation monitors
      • Downstream photon probe is broken.
  • Detector systems
    • ST (Mark Ito)
    • FDC (Lubomir)
    • CDC (Beni)
    • BCal (Elton)
    • FCal (Adesh)
    • TOF (Mark Ito/Beni/Alex. Ostrovidov)
  • Online monitoring (David L.)
  • Calibration/reconstruction/offline monitoring (Paul Mattione)
  • Level 3 Trigger (David L.)
  • Safety documents (Beni):
    • ESAD must be updated to include safety procedure for ComCal. motion.
    • ESAD ready, RSAD should be ready.
  • Hall Status/safety (Tom/Tim)
    • Ready
  • Other topics?