Difference between revisions of "Controls Meeting 15-Nov-2012"
From GlueXWiki
m |
m (Text replacement - "/halldweb1.jlab.org/" to "/halldweb.jlab.org/") |
||
(One intermediate revision by one other user not shown) | |||
Line 11: | Line 11: | ||
* Other controls applications | * Other controls applications | ||
** FCAL, gas system, etc. | ** FCAL, gas system, etc. | ||
− | * [http:// | + | * [http://halldweb.jlab.org/JInventory JInventory improvements] - Josh, Hovanes, Elliott |
** barcode readers and labels, conventions, etc. | ** barcode readers and labels, conventions, etc. | ||
− | * [http:// | + | * [http://halldweb.jlab.org/mantisbt Mantis task tracker] |
− | * [https:// | + | * [https://halldweb.jlab.org/elog-halld Midas elog] |
Line 40: | Line 40: | ||
=Minutes= | =Minutes= | ||
+ | |||
+ | Present: Elliott W, Josh B, Dan B. | ||
+ | |||
+ | |||
+ | We had a relatively short meeting due to low attendance: | ||
+ | |||
+ | * Josh fixed the scan time for the EPICS IOC connection to the PLC. | ||
+ | * Elliott reported on recent hardware installation in the counting house. | ||
+ | * We discussed the Cryo connection to our PLC, PLC alarms, and archiving. | ||
+ | * Josh said the PLC system is ready to go for the Solenoid test. |
Latest revision as of 11:25, 31 March 2015
Agenda
- Announcements
- Minutes from previous meeting 18-Oct-2012
- Counting house - HOvanes, Elliott
- computers, license servers, Windows, monitoring farm, etc.
- Hardware purchase status - Josh, Hovanes
- EPICS - Hovanes
- Solenoid test - Josh, Hovanes, Elliott
- databases, A-B stuff, PXI, data logging, IOC's, elog, EPICS/Labview, etc.
- Other controls applications
- FCAL, gas system, etc.
- JInventory improvements - Josh, Hovanes, Elliott
- barcode readers and labels, conventions, etc.
- Mantis task tracker
- Midas elog
- Experiment Control Supervisor - Elliott
Time/Location
9:30AM Thurs 15-Nov-2012 CC L207
Announcements
Next Meeting
9:30am Thurs 29-Nov-2012
Minutes
Present: Elliott W, Josh B, Dan B.
We had a relatively short meeting due to low attendance:
- Josh fixed the scan time for the EPICS IOC connection to the PLC.
- Elliott reported on recent hardware installation in the counting house.
- We discussed the Cryo connection to our PLC, PLC alarms, and archiving.
- Josh said the PLC system is ready to go for the Solenoid test.