* Minutes from previous meeting [[Controls_Meeting_9-Aug-2012|9-Aug-2012]] | * Minutes from previous meeting [[Controls_Meeting_9-Aug-2012|9-Aug-2012]] | ||
* Hardware purchase status - Josh, Hovanes | * Hardware purchase status - Josh, Hovanes | ||
+ | * Test Stand - Josh | ||
+ | ** SOE, Turbo pump | ||
* EPICS - Hovanes | * EPICS - Hovanes | ||
* Counting house installation - Hovanes | * Counting house installation - Hovanes | ||
− | * [http:// | + | * [http://halldweb.jlab.org/JInventory JInventory improvements] - Elliott |
* Solenoid test - Mark, Josh, Scot, Elliott | * Solenoid test - Mark, Josh, Scot, Elliott | ||
** Fasttrack schedule | ** Fasttrack schedule | ||
** Power supply maintenance OSP | ** Power supply maintenance OSP | ||
− | ** | + | ** Test plan, procedures, operations OSP, review |
** Vacuum, SOE, quench detector, etc. | ** Vacuum, SOE, quench detector, etc. | ||
* PLC programming and PXI system - Josh, Dave, Yi | * PLC programming and PXI system - Josh, Dave, Yi | ||
− | * | + | * Danfysik tutorial part 3 - Sarin P. |
− | + | * [http://halldweb.jlab.org/mantisbt Mantis task tracker] | |
− | * [http:// | + | * [https://halldweb.jlab.org/elog-halld Midas elog] |
− | * [https:// | + | |
+ | |||
* Experiment Control Supervisor - Elliott | * Experiment Control Supervisor - Elliott | ||
+ | * Accelerator Elog - Elliott | ||
Line 25: | Line 29: | ||
==Time/Location== | ==Time/Location== | ||
− | 9:30AM Thurs 9-Aug-2012 CC | + | '''Note change of location''' |
+ | |||
+ | 9:30AM Thurs 9-Aug-2012 CC L102 | ||
Line 41: | Line 47: | ||
=Minutes= | =Minutes= | ||
+ | |||
+ | Present: Elliott W, Mark S, Josh B, Dave B, Sarin P. | ||
+ | |||
+ | |||
+ | '''Most of the meeting was taken up with Sarin's presentation. A few topics were discussed briefly:''' | ||
+ | |||
+ | |||
+ | * End of year "freeze" on 12GEV spending, need to talk with Eugene to get PO's through Procurement for all but the smallest items. | ||
+ | * Josh will order 4- or 8-channel Point I/O analog input module for reading turbopump speeds. | ||
+ | * Still not clear when Nerses will arrive. | ||
+ | * Josh will test turbo in EEL 126. | ||
+ | * SOE still on hold. | ||
+ | * Waiting for a few items to complete above-rack power in Rack Room. | ||
+ | * Will meet with Networking group to get fibers run from Telecom room to Rack room. | ||
+ | * Elliott continues to improve JInventory functionality for housing, power and control hierarchies. | ||
+ | * Solenoid test still on schedule. | ||
+ | * Mark will complete Danfysik work in the next week or two. | ||
+ | * Josh put out second draft of Test Plan. A number of procedures need to be written. | ||
+ | * Josh and George are deriving the THA from the FMEA. | ||
+ | * QD mods still waiting for confirmation from Alexander and/or Fernando. |
Latest revision as of 10:34, 31 March 2015
Agenda
- Announcements
- FPGA programming tutorial by Ben Raydo on 29-Aug at Online meeting
- Beni will talk about the Gas System in early Sep.
- Minutes from previous meeting 9-Aug-2012
- Hardware purchase status - Josh, Hovanes
- Test Stand - Josh
- SOE, Turbo pump
- EPICS - Hovanes
- Counting house installation - Hovanes
- JInventory improvements - Elliott
- Solenoid test - Mark, Josh, Scot, Elliott
- Fasttrack schedule
- Power supply maintenance OSP
- Test plan, procedures, operations OSP, review
- Vacuum, SOE, quench detector, etc.
- PLC programming and PXI system - Josh, Dave, Yi
- Danfysik tutorial part 3 - Sarin P.
- Mantis task tracker
- Midas elog
- Experiment Control Supervisor - Elliott
- Accelerator Elog - Elliott
Time/Location
Note change of location
9:30AM Thurs 9-Aug-2012 CC L102
Announcements
Next Meeting
9:30am Thurs 6-Sep-2012 CC L207
Minutes
Present: Elliott W, Mark S, Josh B, Dave B, Sarin P.
Most of the meeting was taken up with Sarin's presentation. A few topics were discussed briefly:
- End of year "freeze" on 12GEV spending, need to talk with Eugene to get PO's through Procurement for all but the smallest items.
- Josh will order 4- or 8-channel Point I/O analog input module for reading turbopump speeds.
- Still not clear when Nerses will arrive.
- Josh will test turbo in EEL 126.
- SOE still on hold.
- Waiting for a few items to complete above-rack power in Rack Room.
- Will meet with Networking group to get fibers run from Telecom room to Rack room.
- Elliott continues to improve JInventory functionality for housing, power and control hierarchies.
- Solenoid test still on schedule.
- Mark will complete Danfysik work in the next week or two.
- Josh put out second draft of Test Plan. A number of procedures need to be written.
- Josh and George are deriving the THA from the FMEA.
- QD mods still waiting for confirmation from Alexander and/or Fernando.