Difference between revisions of "Trigger Commissioning"
From GlueXWiki
Line 15: | Line 15: | ||
: - adjust trigger parameters, tune timing | : - adjust trigger parameters, tune timing | ||
: - study rates for various trigger thresholds | : - study rates for various trigger thresholds | ||
+ | |||
+ | * '''Add CDC, FDC, BCAL, ST, TOF (TAGM/TAGH ?)''' (2 - 3 days) |
Revision as of 17:25, 14 September 2014
Trigger Commissioning Plan
Phase 1: Photon-beam Commissioning
- PS stand alone trigger (2 - 3 days)
- - trigger with PSC
- - read out PS and PSC
- - trigger distribution through GTP. Use PCS self trigger if problems with GTP
Phase 2: Photon Beam in the Hall
- Tune FCAL trigger (2 - 3 days)
- - trigger using global energy
- - read out FCAL only. Raw mode for fadc250
- - adjust trigger parameters, tune timing
- - study rates for various trigger thresholds
- Add CDC, FDC, BCAL, ST, TOF (TAGM/TAGH ?) (2 - 3 days)