Difference between revisions of "Trigger Commissioning"
From GlueXWiki
Line 4: | Line 4: | ||
* '''PS stand alone trigger''' (2 - 3 days) | * '''PS stand alone trigger''' (2 - 3 days) | ||
− | : | + | : - trigger with PSC |
− | : | + | : - read out PS and PSC |
− | : | + | : - trigger distribution through GTP. Use PCS self trigger if problems with GTP |
+ | |||
+ | === Phase 2: Photon Beam in the Hall === | ||
+ | |||
+ | * '''Tune FCAL trigger''' (2 - 3 days) | ||
+ | : - trigger using global energy | ||
+ | : - read out FCAL only. Raw mode for fadc250 | ||
+ | : - adjust trigger parameters, tune timing | ||
+ | : - study rates for various trigger thresholds |
Revision as of 17:23, 14 September 2014
Trigger Commissioning Plan
Phase 1: Photon-beam Commissioning
- PS stand alone trigger (2 - 3 days)
- - trigger with PSC
- - read out PS and PSC
- - trigger distribution through GTP. Use PCS self trigger if problems with GTP
Phase 2: Photon Beam in the Hall
- Tune FCAL trigger (2 - 3 days)
- - trigger using global energy
- - read out FCAL only. Raw mode for fadc250
- - adjust trigger parameters, tune timing
- - study rates for various trigger thresholds