Difference between revisions of "Photon Beam Commissioning Discussion Aug 20, 2014"
From GlueXWiki
(→Agenda) |
|||
Line 33: | Line 33: | ||
''Attending: | ''Attending: | ||
+ | |||
+ | # Announcements | ||
+ | # Recommendations from [http://www.jlab.org/Hall-D/halld_secure/reviews/ERR_HallD_Jul2014/Final_Report_HallD_Experiment_Readiness_Review.pdf ERR Report] | ||
+ | # Aug 8 Photon Beam Commissioning Review [http://www.jlab.org/Hall-D/halld_secure/reviews/PhotonBeamCommissioning_Internal_Aug2014/Final_Report/ReportonPhotonBeamCommissioning.pdf Final Report] | ||
+ | # ARR presentations | ||
+ | # Accelerator and Hall D Interface Document - needs to be finalized. | ||
+ | # Update on Photon Commissioning (Alexandre) | ||
+ | # [[Beam Simulations]] | ||
+ | # RadCon update | ||
+ | # Other business |
Revision as of 08:43, 21 August 2014
Organization
- Time: 4 pm EST
- Connecting: detailed instructions are here
- H.323 ip address: 199.48.152.152
- web browser: https://bluejeans.com/536076821
- phone: 408-740-7256 or 888-240-2560
- Conference id: 536076821
References
Action Items
- Send Todd a geometry of tagger area, including the mapped tagger magnet field, for GEANT simulations (Richard). Richard is working to update the defined geometry based on a drawing received from Tim, Richard will add field map from Dan Sober
- Estimate rates and ranges of parameters needed for the photon beam tuning (Todd for accelerator; Elton, Hovanes, Eugene, Alexandre for Hall D)
- Need rates for profiler, start counter, ps
- Richard will provide a "sacrificial" board with 30 SiPMs to register neutron damage during initial electron beam tune.
- Hovanes is preparing photomultipliers that can be used to measure beam loss along the beamline.
- Alexandre will meet with RadCon next week to coordinate details of accessing monitor information
Agenda
- Announcements
- Recommendations from ERR Report
- Aug 8 Photon Beam Commissioning Review Final Report
- ARR presentations
- Accelerator and Hall D Interface Document - needs to be finalized.
- Update on Photon Commissioning (Alexandre)
- Beam Simulations
- RadCon update
- Other business
Minutes
Attending:
- Announcements
- Recommendations from ERR Report
- Aug 8 Photon Beam Commissioning Review Final Report
- ARR presentations
- Accelerator and Hall D Interface Document - needs to be finalized.
- Update on Photon Commissioning (Alexandre)
- Beam Simulations
- RadCon update
- Other business