Difference between revisions of "BCAL Startup Checkout List 2014"
From GlueXWiki
(→Slow Controls) |
(→Slow Controls) |
||
Line 17: | Line 17: | ||
* Read back of RTDs on cooling plates upstream | * Read back of RTDs on cooling plates upstream | ||
* Read back of RTDs on cooling plates downstream | * Read back of RTDs on cooling plates downstream | ||
− | * Check temperatures and humidity | + | * Check temperatures and humidity conditions |
* Install interlock of chiller and MPPC power to humidity and temperature signals (long term). For now manual check. | * Install interlock of chiller and MPPC power to humidity and temperature signals (long term). For now manual check. | ||
Revision as of 09:22, 13 February 2014
DAQ
- Initial readout of pedestals (3 crates)
- Install remaining CPUs
- Readout FADC and F1 TDC crates (MPPCs off)
Chiller
- Make connections from chiller to manifold ring
- Get power connections to chiller
- Check operation of cooling loop
N2 flow
- Install flow meters symmetrically on upstream and downstream
Slow Controls
- Read back T and Humidity upstream
- Read back T and Humidity downstream
- Read back of RTDs on cooling plates upstream
- Read back of RTDs on cooling plates downstream
- Check temperatures and humidity conditions
- Install interlock of chiller and MPPC power to humidity and temperature signals (long term). For now manual check.
Set Power MPPCs
- Connection to network
- Check that data base has correct bias information
- Turn on bias one by one and make initial checks with scope
LED monitoring
- Replace translation boards with correct pin assignments
- Install MOD crate
- Complete cabling to crate
- Connect MPOD and VME crates to network