Difference between revisions of "GlueX Data Challenge Meeting, January 31, 2014"
From GlueXWiki
(Created page with "GlueX Data Challenge Meeting<br> Monday, January 31, 2014<br> 11:30 pm, EDT<br> JLab: CEBAF Center, F326/327 =Agenda= # Announcements # Status of Preparations # Proposed Schedu...") |
(→Agenda) |
||
Line 8: | Line 8: | ||
# Announcements | # Announcements | ||
# Status of Preparations | # Status of Preparations | ||
+ | ## Finish reversed magnetic field fixes. | ||
+ | ## Do we have standard build/submission stuff to run the challenge? | ||
+ | ## Are we ready to produce the event sample? | ||
+ | ## Test jobs with EM background to make sure that data size is reasonable and we are not introducing crashes. | ||
+ | ## Target Distribution (where?). | ||
+ | ## Test jobs in general with the updated REST format to check new data footprint. | ||
+ | ## Pre-load sets of jobs with ~100 runs on the clusters participating in the data challenge to make sure that things run. | ||
+ | ## Is the JLab CC ready for us? | ||
+ | ## What ability will we have for SRM at Jefferson Lab? | ||
# Proposed Schedule | # Proposed Schedule | ||
# AOT | # AOT |
Revision as of 16:49, 30 January 2014
GlueX Data Challenge Meeting
Monday, January 31, 2014
11:30 pm, EDT
JLab: CEBAF Center, F326/327
Agenda
- Announcements
- Status of Preparations
- Finish reversed magnetic field fixes.
- Do we have standard build/submission stuff to run the challenge?
- Are we ready to produce the event sample?
- Test jobs with EM background to make sure that data size is reasonable and we are not introducing crashes.
- Target Distribution (where?).
- Test jobs in general with the updated REST format to check new data footprint.
- Pre-load sets of jobs with ~100 runs on the clusters participating in the data challenge to make sure that things run.
- Is the JLab CC ready for us?
- What ability will we have for SRM at Jefferson Lab?
- Proposed Schedule
- AOT