== Installation == | == Installation == | ||
− | - Bill, Casey, and Dave glued the 16 reflectors to the gussets of the packages (four per package). The survey group started working on the new targets yesterday and they are working now. Preliminary findings: if looking along z they found distance between the first and last package to the be the same as the measured one within 0.5mm (measured with measuring tape?). They also | + | - FDC was moved on the floor on Monday. Bill, Casey, and Dave glued the 16 reflectors to the gussets of the packages (four per package). The survey group started working on the new targets yesterday and they are working now. Preliminary findings: if looking along z they found distance between the first and last package to the be the same as the measured one within 0.5mm (measured with measuring tape?). However, they found that this is no longer the case if you look at some angle (w.r.t. the normal of the reflectors), as Eugene expected. They are now trying to find what is the range of the angles that is acceptable. They were also instructed to redo all the surveys they did before: the four SMR holders on each package and the flatness measurements. |
== Engineering == | == Engineering == | ||
− | - | + | - We discussed again the previous survey results. Even, as stated at the last meeting Bill found |
== Electronics == | == Electronics == |
Revision as of 18:23, 14 November 2013
November 14, 2013 FDC meeting
Agenda
- Installation status[1]
- Engineering (Bill)
- FDC survey
- Cooling system
- Electronics (Chris, Nick)
- Mini-DAQ for FDC tests (Beni)
- Full electronics test analyses (Lubomir)
- Other