Difference between revisions of "BLTWG Meeting 09/16/2013"
From GlueXWiki
(→Agenda) |
|||
Line 10: | Line 10: | ||
# [[GlueX-Collaboration-Oct-2013|October Collaboration Meeting]] | # [[GlueX-Collaboration-Oct-2013|October Collaboration Meeting]] | ||
# Update on mapping - ''Tim W.'' | # Update on mapping - ''Tim W.'' | ||
− | |||
# Update on pair spectrometer - ''Ivan T.'' | # Update on pair spectrometer - ''Ivan T.'' | ||
# [http://argus.phys.uregina.ca/cgi-bin/private/DocDB/ShowDocument?docid=2294 TAGH counter inspection and testing] - ''Franz K./Natalie W.'' | # [http://argus.phys.uregina.ca/cgi-bin/private/DocDB/ShowDocument?docid=2294 TAGH counter inspection and testing] - ''Franz K./Natalie W.'' | ||
# Update on goniometer testing - ''Yi Q.'' | # Update on goniometer testing - ''Yi Q.'' | ||
# Update on clock signal - ''Eugene C.'' | # Update on clock signal - ''Eugene C.'' | ||
+ | # Update on microscope electronics - ''Alex B.'' | ||
# [http://argus.phys.uregina.ca/cgi-bin/private/DocDB/ShowDocument?docid=2181 Status of the microscope construction] - ''James M.'' | # [http://argus.phys.uregina.ca/cgi-bin/private/DocDB/ShowDocument?docid=2181 Status of the microscope construction] - ''James M.'' | ||
− | # Diamond thinning proposal - ''Jarrod F.'' | + | # Diamond thinning proposal - ''Brenden/Jarrod F.'' |
#''any other business'' | #''any other business'' | ||
+ | |||
+ | ===Minutes=== | ||
+ | # Mapping - ''Tim'' | ||
+ | ## preparing mapping instrument for tagger magnet | ||
+ | ## repairing power supply for the pair spectrometer's magnet | ||
+ | # Pair spectrometer - ''Ivan'' | ||
+ | ## all parts are ready except for the fixture of the fibers, working with Chuck on design | ||
+ | ## working on slow control | ||
+ | # Fixed array - ''Natalie'' | ||
+ | ## received all scintillator bars with light guide glued | ||
+ | ## checked all of them, most of them are good | ||
+ | ## working on final design of the holder | ||
+ | # Microscope - ''Alex B.'' | ||
+ | ## production on track, will ship samples to JLab soon | ||
+ | # Microscope construction - ''James'' | ||
+ | ## a little bit late on first article, but the whole schedule and budget are still on track | ||
+ | # Diamond thinning - ''Brenden/Jarrod'' | ||
+ | ## restarting the thinning process | ||
+ | ## Jarrod working with Richard on the proposal | ||
+ | # Goniometer - ''Yi'' | ||
+ | ## Testing goniometer in FEL | ||
+ | ## verified minimum step sized: 0.2 mdeg in yaw and 0.1 mdeg in pitch | ||
+ | ## more test on reproducibility and optimize moving parameters | ||
+ | # Accelerator Clock - ''Eugene'' | ||
+ | ## going to order cable for the signal form physics's FY14 budget |
Revision as of 10:41, 18 September 2013
Organization
- Time: 11:30 EST
- Place: ESNET and Seevogh (Jlab community)
- Connecting: instructions are here
- Present: Natalie W., Jarrod F., Eugene C., Todd S., Ivan T., Tim W., Yi Q., Brenden P., Alex B., Ann C., James M., Curtis M., Franz K.
Agenda
- Announcements
- October Collaboration Meeting
- Update on mapping - Tim W.
- Update on pair spectrometer - Ivan T.
- TAGH counter inspection and testing - Franz K./Natalie W.
- Update on goniometer testing - Yi Q.
- Update on clock signal - Eugene C.
- Update on microscope electronics - Alex B.
- Status of the microscope construction - James M.
- Diamond thinning proposal - Brenden/Jarrod F.
- any other business
Minutes
- Mapping - Tim
- preparing mapping instrument for tagger magnet
- repairing power supply for the pair spectrometer's magnet
- Pair spectrometer - Ivan
- all parts are ready except for the fixture of the fibers, working with Chuck on design
- working on slow control
- Fixed array - Natalie
- received all scintillator bars with light guide glued
- checked all of them, most of them are good
- working on final design of the holder
- Microscope - Alex B.
- production on track, will ship samples to JLab soon
- Microscope construction - James
- a little bit late on first article, but the whole schedule and budget are still on track
- Diamond thinning - Brenden/Jarrod
- restarting the thinning process
- Jarrod working with Richard on the proposal
- Goniometer - Yi
- Testing goniometer in FEL
- verified minimum step sized: 0.2 mdeg in yaw and 0.1 mdeg in pitch
- more test on reproducibility and optimize moving parameters
- Accelerator Clock - Eugene
- going to order cable for the signal form physics's FY14 budget