# Decide on size of overlap of voltage bins for the SiPMs (Yi and Jack) | # Decide on size of overlap of voltage bins for the SiPMs (Yi and Jack) | ||
# Complete molds for wrapping and order forms (Jim) | # Complete molds for wrapping and order forms (Jim) | ||
+ | # Thermal mats need to be ordered (Jim said that Fernando or Chris will take care of this) | ||
== Tentative Agenda == | == Tentative Agenda == |
Revision as of 16:17, 5 July 2012
Action Items from previous meetings
- Develop front and back views of jumper sheets. (Jack)
- Check into AC units based on Peltier coolers for SiPM production tests (Fernando)
- Review Fcal LED and controller monitoring boards (Fernando)
- Decide on size of overlap of voltage bins for the SiPMs (Yi and Jack)
- Complete molds for wrapping and order forms (Jim)
- Thermal mats need to be ordered (Jim said that Fernando or Chris will take care of this)
Tentative Agenda
- Announcements
- Action Items
- Schedule, reporting, and manpower (Elton)
- SiPM production testing (everyone)
- SiPMs assignment for new boards
- Mechanical assembly (Jim)
- Temperature compensation (Jack)
- Electronic boards (Chris)
- Light guide gluing setup
Minutes
Attending: