Difference between revisions of "Feb 24, 2011 SiPM Electrical and Cooling"
From GlueXWiki
(→Action Items from previous meetings) |
(→Action Items from previous meetings) |
||
Line 8: | Line 8: | ||
# Check current draw of SiPMs during beam conditions (Yi and Carl) | # Check current draw of SiPMs during beam conditions (Yi and Carl) | ||
+ | # Provide thermistor data sheet to Jim (Jack) | ||
+ | # Get cable specs to Jim (Fernando) | ||
== Tentative Agenda == | == Tentative Agenda == |
Revision as of 18:04, 17 February 2011
References
- Files for discussion
- Hall D BCAL Readout Mechanical Concept (Jim Fochtman)
- Dynamic Range (See section 6 under simulations)
Action Items from previous meetings
- Check current draw of SiPMs during beam conditions (Yi and Carl)
- Provide thermistor data sheet to Jim (Jack)
- Get cable specs to Jim (Fernando)
Tentative Agenda
- Announcements
- Schedule, reporting, and manpower (Elton)
- First article testing (Carl and Yi)
- Mechanical cooling (Jim)
- Temperature compensation (Jack)
- Preamp-summing (Fernando)
- Discussion
Minutes
Attending:
Attendees: