Difference between revisions of "Coil Test Weekly Meeting 28-Jan-2011"

From GlueXWiki
Jump to: navigation, search
m
m
 
(2 intermediate revisions by the same user not shown)
Line 4: Line 4:
 
'''Location and Time'''
 
'''Location and Time'''
  
* Fri 28-Jan-2011 9:30 am ARC 428
+
* Mon 31-Jan-2011 9:30 am ARC 528
  
 +
'''(switched to Mon due to Director's meeting Fri 9:30am)'''
  
'''Note no meeting next week due to collaboration meeting'''
+
 
 +
'''Note: no meeting Fri 4-Feb-2011 due to GlueX collaboration meeting'''
  
  
Line 25: Line 27:
 
* [[For_the_second_coil|To-do list]] for the next coil
 
* [[For_the_second_coil|To-do list]] for the next coil
 
* Coil 3 strategy
 
* Coil 3 strategy
 +
** should we test coil in vertical position?
 
* Coil 2 repair status
 
* Coil 2 repair status
 
* Status of abstract submission and paper - George
 
* Status of abstract submission and paper - George
 
* Preparing for moving into the hall
 
* Preparing for moving into the hall

Latest revision as of 10:04, 31 January 2011

Solenoid Coil Test Weekly Meeting

Location and Time

  • Mon 31-Jan-2011 9:30 am ARC 528

(switched to Mon due to Director's meeting Fri 9:30am)


Note: no meeting Fri 4-Feb-2011 due to GlueX collaboration meeting


Agenda

  • Update on installation progress
  • Coil taps and Dataforth system - Elliott
    • voltage attenuators, dividers, NI device protection
    • input impedance and overcurrent protection resistor size
  • Danfysik slow dump, offset voltage, ground fault detection - Mark, Cody
  • Quench detector - Elliott
  • Should we test the magnet and quench detector at low Danfysik current?
  • A-B licenses, software, computers - Josh
  • HMI logging, database, computers - Yi
  • EPICS status - Hovanes
  • To-do list for the next coil
  • Coil 3 strategy
    • should we test coil in vertical position?
  • Coil 2 repair status
  • Status of abstract submission and paper - George
  • Preparing for moving into the hall