Difference between revisions of "Coil Test Weekly Meeting 28-Jan-2011"
From GlueXWiki
m |
|||
Line 11: | Line 11: | ||
* Update on installation progress | * Update on installation progress | ||
* Coil taps and Dataforth system - Elliott | * Coil taps and Dataforth system - Elliott | ||
− | ** voltage attenuators | + | ** voltage attenuators, dividers, NI device protection |
** input impedance and overcurrent protection resistor size | ** input impedance and overcurrent protection resistor size | ||
− | * Danfysik offset - Mark, Cody | + | * Danfysik slow dump, offset voltage, ground fault detection - Mark, Cody |
+ | * Quench detector - Elliott | ||
+ | * A-B licenses, software, computers - Josh | ||
+ | * HMI logging, database, computers - Yi | ||
+ | * EPICS status - Hovanes | ||
* [[For_the_second_coil|To-do list]] for the next coil | * [[For_the_second_coil|To-do list]] for the next coil | ||
* Coil 3 strategy | * Coil 3 strategy |
Revision as of 10:21, 27 January 2011
Solenoid Coil Test Weekly Meeting
Location and Time
- Fri 28-Jan-2011 9:30 am ARC 428
Agenda
- Update on installation progress
- Coil taps and Dataforth system - Elliott
- voltage attenuators, dividers, NI device protection
- input impedance and overcurrent protection resistor size
- Danfysik slow dump, offset voltage, ground fault detection - Mark, Cody
- Quench detector - Elliott
- A-B licenses, software, computers - Josh
- HMI logging, database, computers - Yi
- EPICS status - Hovanes
- To-do list for the next coil
- Coil 3 strategy
- Coil 2 repair status
- Status of abstract submission and paper - George
- Preparing for moving into the hall