Difference between revisions of "For the second coil"
From GlueXWiki
m |
m |
||
Line 1: | Line 1: | ||
* Basic questions | * Basic questions | ||
+ | ** lag between field and current...are there turn-to-turn shorts? | ||
** what worked, what didn't for coil 1? | ** what worked, what didn't for coil 1? | ||
** what should we do differently for the next coil? | ** what should we do differently for the next coil? | ||
Line 10: | Line 11: | ||
* Puzzles and problems to be addressed before next coil test | * Puzzles and problems to be addressed before next coil test | ||
** improve cryo system | ** improve cryo system | ||
+ | *** minimize ice buildup | ||
+ | *** more heating/insulation on N2 vent line | ||
*** cold traps | *** cold traps | ||
** field polarity reversed | ** field polarity reversed | ||
Line 17: | Line 20: | ||
** other wiring, cable and connector problems | ** other wiring, cable and connector problems | ||
** total coil inductance disagreement | ** total coil inductance disagreement | ||
+ | ** dynamic range adjustments | ||
+ | ** noise elimination | ||
** slow dump doesn't work | ** slow dump doesn't work | ||
** understand fast dump circuit | ** understand fast dump circuit |
Revision as of 12:53, 17 December 2010
- Basic questions
- lag between field and current...are there turn-to-turn shorts?
- what worked, what didn't for coil 1?
- what should we do differently for the next coil?
- what coil will we test next?
- what might we consider doing differently in the hall?
- distinguish between "must haves" vs "should haves" vs "would like to haves"
- have we documented our experience?
- Puzzles and problems to be addressed before next coil test
- improve cryo system
- minimize ice buildup
- more heating/insulation on N2 vent line
- cold traps
- field polarity reversed
- sub-coil inductances appear to be backwards
- inductance seen on splices
- USB device wiring problems
- other wiring, cable and connector problems
- total coil inductance disagreement
- dynamic range adjustments
- noise elimination
- slow dump doesn't work
- understand fast dump circuit
- measure fast dump resistances
- understand Danfysik ramp-down mechanism
- vapor-cooled lead blockage
- can anything be done to avoid another one?
- cold traps
- heaters
- improve ability to adjust quench detector
- bring test points to front panel
- use matched resistors
- use new sensor for vapor-cooled lead voltage drop
- isolation and current-loop readout for critical signals
- interaction via Zener and Dataforth clipping
- UPS on Danfysik boards and contactor
- improve PLC cryo and MPS algorithms (in preparation for non-expert use)
- simplify many operations
- improve PLC early problem detection
- improve PLC cryo control under varying CTF operating conditions
- add more HMI screens (may need license upgrade)
- simplify existing screens
- additional HMI license, get second computer working
- more pre-defined trend plots
- did we ever implement guard shack notification?
- automated elog entries
- update drawings and documentation
- where is manpower to make improvements?
- what else?
- improve cryo system