* DOE review 28-Sep - George, Elliott | * DOE review 28-Sep - George, Elliott | ||
** final status for Glenn's talk | ** final status for Glenn's talk | ||
+ | ** preparation for visit to Test Lab by reviewers | ||
* Conduct of Operations - Josh, Elliott | * Conduct of Operations - Josh, Elliott | ||
** results of Wed meeting | ** results of Wed meeting | ||
Line 20: | Line 21: | ||
** when do we give two weeks notice to Errol? | ** when do we give two weeks notice to Errol? | ||
* Test plan - Josh | * Test plan - Josh | ||
+ | ** addition of check valve and relief valve in lead flow system | ||
* Magnet power supply and interlock commissioning - Cody | * Magnet power supply and interlock commissioning - Cody | ||
** latest status | ** latest status | ||
Line 40: | Line 42: | ||
** tutorial? | ** tutorial? | ||
* Coil repair status - George | * Coil repair status - George | ||
+ | * Solenoid review 25-26 Oct | ||
* Preparations for testing next coil - George, Elliott | * Preparations for testing next coil - George, Elliott | ||
** update P&I | ** update P&I |
Revision as of 16:59, 20 September 2010
Solenoid Coil Test Weekly Meeting
Location and Time
- Thu 23-Sep-2010 9:30am ARC 428
Agenda
- DOE review 28-Sep - George, Elliott
- final status for Glenn's talk
- preparation for visit to Test Lab by reviewers
- Conduct of Operations - Josh, Elliott
- results of Wed meeting
- OSP documents and review - Elliott, George
- what is left to do?
- when can/must we turn everything in?
- Installation status
- what's left?
- when do we give two weeks notice to Errol?
- Test plan - Josh
- addition of check valve and relief valve in lead flow system
- Magnet power supply and interlock commissioning - Cody
- latest status
- Controls racks - Scot
- strain gauge interlock
- UPS interlock
- anything else?
- PLC programming/testing status - Mark W
- UPS interlock
- guard shack
- what's left?
- backup PLC programmer?
- tutorial?
- EPICS <--> PLC communications - Wesley
- PV list from Jonathan Creel
- under what circumstances do we notify the guard shack?
- HMI and EWEB programming - Yi, Hovanes
- Josh's screens
- current status
- tutorial?
- Coil repair status - George
- Solenoid review 25-26 Oct
- Preparations for testing next coil - George, Elliott
- update P&I
- splices
- yoke location
- piping adaptors
- downstream yoke spacers