* F117 status - Elliott | * F117 status - Elliott | ||
** when to move PLC to F117 for testing? | ** when to move PLC to F117 for testing? | ||
− | ** hole in the wall? | + | ** schedule for hole in the wall, door? |
* B field - George, Floyd | * B field - George, Floyd | ||
** at power supply | ** at power supply | ||
** where to place racks? | ** where to place racks? | ||
* Safety review - Elliott | * Safety review - Elliott | ||
− | ** | + | ** agenda |
** 2-Jul meeting date, 23-Jun deadline submit writing assignments to me, 25-Jun submit documents to committee | ** 2-Jul meeting date, 23-Jun deadline submit writing assignments to me, 25-Jun submit documents to committee | ||
*** George - pressure (Steve L), large mechanical structures (John K and/or Suresh), B field (Jennifer W) | *** George - pressure (Steve L), large mechanical structures (John K and/or Suresh), B field (Jennifer W) | ||
Line 34: | Line 34: | ||
* EPICS <--> PLC communications - Wesley | * EPICS <--> PLC communications - Wesley | ||
* Relay cards (for open collector outputs) - Cody | * Relay cards (for open collector outputs) - Cody | ||
− | * Controls racks - | + | * Controls racks - Scot |
** wiring diagram update | ** wiring diagram update | ||
+ | ** any remaining work? | ||
* PLC programming status - Mark W | * PLC programming status - Mark W | ||
+ | ** testing in F117? | ||
* HMI and EWEB programming - Yi, Elliott | * HMI and EWEB programming - Yi, Elliott | ||
* Printer, laptop - Elliott | * Printer, laptop - Elliott |
Latest revision as of 16:11, 16 June 2010
Solenoid Coil Test Weekly Meeting
Note: short meeting due to Solenoid meeting at 11am
Location and Time
- Thu 17-Jun-2010 9:30am ARC 428
Agenda
- F117 status - Elliott
- when to move PLC to F117 for testing?
- schedule for hole in the wall, door?
- B field - George, Floyd
- at power supply
- where to place racks?
- Safety review - Elliott
- agenda
- 2-Jul meeting date, 23-Jun deadline submit writing assignments to me, 25-Jun submit documents to committee
- George - pressure (Steve L), large mechanical structures (John K and/or Suresh), B field (Jennifer W)
- Josh - ODH (Mat), cryo supply (Mat), cryo devices (Mat)
- Cody - magnet power (Bill Merz)
- Elliott - controls (Steve L)
- list of previous reviews
- Coil test plan - Josh
- Magnet power supply commissioning - Cody
- status
- dump resistor
- magnetic field
- EPICS <--> PLC communications - Wesley
- Relay cards (for open collector outputs) - Cody
- Controls racks - Scot
- wiring diagram update
- any remaining work?
- PLC programming status - Mark W
- testing in F117?
- HMI and EWEB programming - Yi, Elliott
- Printer, laptop - Elliott
- Installation status - George
- Coil repair status - George
- DOE mandated coil replacement plan status - George, Elliott