Difference between revisions of "Coil Test Weekly Meeting 17-Jun-2010"

From GlueXWiki
Jump to: navigation, search
 
m
Line 36: Line 36:
 
** dump resistor
 
** dump resistor
 
** magnetic field
 
** magnetic field
** upgrade to higher current
 
 
* EPICS <--> PLC communications - Wesley
 
* EPICS <--> PLC communications - Wesley
* Quick report from EPICS collaboration meeting - Wesley
+
* Relay cards (for open collector outputs) - Cody
* Final equipment orders - Elliott
+
* Controls racks - Mark W, Scot
** A-B components
+
** wiring diagram update
** relay cards (for open collector outputs)
+
** anything else?
+
* Wiring and testing controls racks - Scot
+
** how much testing can be done in F117?
+
** how much needs the PLC?
+
** how to prepare for next coil to be tested?
+
** who will update wiring diagrams?
+
 
* PLC programming status - Mark W
 
* PLC programming status - Mark W
** C-glass calibrations - Elliott
 
 
* HMI and EWEB programming - Yi, Elliott
 
* HMI and EWEB programming - Yi, Elliott
** 25 screen limit
+
* Printer, laptop - Elliott
** dual-monitors
+
** do we need a printer?
+
** do we need laptops?
+
 
* Installation status - George
 
* Installation status - George
 
* Coil repair status - George
 
* Coil repair status - George
 
* DOE mandated coil replacement plan status - George, Elliott
 
* DOE mandated coil replacement plan status - George, Elliott

Revision as of 13:30, 16 June 2010

Solenoid Coil Test Weekly Meeting

Location and Time

  • Thu 10-Jun-2010 9:30am ARC 428


Agenda

  • F117 status - Tim, Elliott
    • when must we vacate to make room for others? shortly after 16-Jul?
    • is there enough room now for Fernando et al?
    • note that hole in wall scheduled for 16-Jul
    • wiring should be done by 15-Jun, wire testing about a week later
    • how long does Mark W need test PLC program?
  • B field - George, Floyd
    • what is field at power supply?
      • if too high, move it? field clamp?
    • where to place controls racks (may not need RS485)?
      • cannot handle high fields
    • where to place computers?
      • cannot handle high fields
  • Safety review - Elliott
    • 2-Jul meeting date
    • 23-Jun deadline submit writing assignments to me (Elton thinks I'll need more time)
    • 25-Jun submit documents to committee
    • writing assignments (SME):
      • George - pressure (Steve L), large mechanical structures (John K and/or Suresh), B field (Jennifer W)
      • Josh - ODH (Mat), cryo supply (Mat), cryo devices (Mat)
      • Cody - magnet power (Bill Merz)
      • Elliott - controls (Steve L)
    • also need coil test plan from George and Josh, list of previous reviews
  • Coil test plan - Josh
  • Magnet power supply commissioning - Cody
    • dump resistor
    • magnetic field
  • EPICS <--> PLC communications - Wesley
  • Relay cards (for open collector outputs) - Cody
  • Controls racks - Mark W, Scot
    • wiring diagram update
  • PLC programming status - Mark W
  • HMI and EWEB programming - Yi, Elliott
  • Printer, laptop - Elliott
  • Installation status - George
  • Coil repair status - George
  • DOE mandated coil replacement plan status - George, Elliott