Difference between revisions of "Minutes-4-15-2010"
Line 16: | Line 16: | ||
# Other | # Other | ||
− | + | ||
= Minutes = | = Minutes = | ||
− | Participants: | + | Participants: Fernando, Eugene, Roger, Drew, Brian, Glenn, Mark, Kim, Simon, Beni, Lubomir |
− | Lubomir | + | |
+ | == Production == | ||
+ | |||
+ | - The property at Blue Crab has been rented by JLab. Hall D will have to pay for our infrastructure inside the bay area, therefore it has to be planned carefully (Eugene). | ||
− | + | - We discussed different options for the wire stringing. The main criteria we use to choose the right one are: demonstrated capabilities of producing operational wire frames, cleanliness of the facility, efforts required to adapt to machines for our purposes. The IUCF doesn't satisfy the above. For now the plan is to investigate the option of using the UVA equipment and expertise to set-up wire stringing at JLab. By chance, Drew and Brian will be at UVA tomorrow (presenting their new Si-detector for medical purposes) and were interested in looking at the UVA wire stringing equipment. Brian expressed the interest of the Detector group to investigate the possibility of having a JLab wire winding facility and one option would be to refurbish the SSC winding machine, now at JLab. | |
+ | Most of the participants asked questions related the modifications needed to have the machine operational. These modifications needs to be evaluated and compared to the ones for the UVA stuff. | ||
− | + | == Updates on: == |
Revision as of 18:20, 15 April 2010
April 8, 2010 FDC meeting
Tentative Agenda
- Production
- Update on the off-site production space floor plan
- Wire winding options: IUCF, JLab using UVA equipment, or using SSC winding machine (Lubomir, Bill, Brian)
- Updates on:
- Electronics: finalizing the PCB design Readout_left, HV_right, HV_left, Readout_right (Fernando, Kim)
- Cathode redesign (Bill, Roger)
- Tests of the new frame prototype (Lubomir)
- Full scale prototype
- Three-layer HV tests (Beni)
- Preparations for cosmics tests
- Other
Minutes
Participants: Fernando, Eugene, Roger, Drew, Brian, Glenn, Mark, Kim, Simon, Beni, Lubomir
Production
- The property at Blue Crab has been rented by JLab. Hall D will have to pay for our infrastructure inside the bay area, therefore it has to be planned carefully (Eugene).
- We discussed different options for the wire stringing. The main criteria we use to choose the right one are: demonstrated capabilities of producing operational wire frames, cleanliness of the facility, efforts required to adapt to machines for our purposes. The IUCF doesn't satisfy the above. For now the plan is to investigate the option of using the UVA equipment and expertise to set-up wire stringing at JLab. By chance, Drew and Brian will be at UVA tomorrow (presenting their new Si-detector for medical purposes) and were interested in looking at the UVA wire stringing equipment. Brian expressed the interest of the Detector group to investigate the possibility of having a JLab wire winding facility and one option would be to refurbish the SSC winding machine, now at JLab. Most of the participants asked questions related the modifications needed to have the machine operational. These modifications needs to be evaluated and compared to the ones for the UVA stuff.