Difference between revisions of "Coil Test Weekly Meeting 1-Apr-2010"

From GlueXWiki
Jump to: navigation, search
m
m
 
(2 intermediate revisions by the same user not shown)
Line 9: Line 9:
 
'''Agenda'''
 
'''Agenda'''
  
 +
* Additional manpower - Tim
 
* How many computers and monitors do we need - All
 
* How many computers and monitors do we need - All
 
* halldusers account on halldsc2 and halldsc3 - Elliott
 
* halldusers account on halldsc2 and halldsc3 - Elliott
Line 15: Line 16:
 
** What is the next step
 
** What is the next step
 
** OSP writing assignments and subject matter experts
 
** OSP writing assignments and subject matter experts
* Progress concerning [http://halldeweb1.jlab.org/user/web/angle.html EWEB module], HMI programming, UPS, terminal server, etc. - Elliott, Yi
+
* Progress concerning EWEB [http://halldeweb1.jlab.org DataViews] and [http://halldeweb1.jlab.org/user/web/angle.html GUI programming], HMI programming, UPS, terminal server, etc. - Elliott, Yi
 
* EPICS connection to PLC - Elliott
 
* EPICS connection to PLC - Elliott
 
* P&I and wiring diagrams, machine protection diagrams, failure scenario analysis - Josh, Scot, Mark S
 
* P&I and wiring diagrams, machine protection diagrams, failure scenario analysis - Josh, Scot, Mark S
 
* Status of PLC programming - Mark W
 
* Status of PLC programming - Mark W
 +
** calibrations
 
* Progress towards testing PLC program in 101 and F117 - Mark W, Scot, Mark S
 
* Progress towards testing PLC program in 101 and F117 - Mark W, Scot, Mark S
 
* What PLC display pages are needed (HMI and web) - Josh
 
* What PLC display pages are needed (HMI and web) - Josh

Latest revision as of 08:50, 1 April 2010

Solenoid Coil Test Weekly Meeting

Location and Time

  • Thu 1-Apr-2010 9:45am ARC 428


Agenda

  • Additional manpower - Tim
  • How many computers and monitors do we need - All
  • halldusers account on halldsc2 and halldsc3 - Elliott
  • Drill press - Mark S, Scot
  • Safety review and progress towards getting OSP and COO - Elliott, Josh, Tim
    • What is the next step
    • OSP writing assignments and subject matter experts
  • Progress concerning EWEB DataViews and GUI programming, HMI programming, UPS, terminal server, etc. - Elliott, Yi
  • EPICS connection to PLC - Elliott
  • P&I and wiring diagrams, machine protection diagrams, failure scenario analysis - Josh, Scot, Mark S
  • Status of PLC programming - Mark W
    • calibrations
  • Progress towards testing PLC program in 101 and F117 - Mark W, Scot, Mark S
  • What PLC display pages are needed (HMI and web) - Josh
  • Wiring progress in F117 - Scot
  • Installation progress - Tom
  • Tying into existing vent piping system - Tom
  • Status of all parts orders - George
  • Coil 1 repair status - George
  • Coil 2 repair status - George
  • Coil 3 progress at IUCF - George
  • Coil 4 controls wiring replacement - George
  • 5 G contours - George