** OSP writing assignments and subject matter experts
 
** OSP writing assignments and subject matter experts
 
* Progress concerning [http://halldeweb1.jlab.org/user/web/angle.html EWEB module], HMI programming, UPS, terminal server, etc. - Elliott, Yi
 
* Progress concerning [http://halldeweb1.jlab.org/user/web/angle.html EWEB module], HMI programming, UPS, terminal server, etc. - Elliott, Yi
 +
* EPICS connection to PLC - Elliott
 
* P&I and wiring diagrams, machine protection diagrams, failure scenario analysis - Josh, Scot, Mark S
 
* P&I and wiring diagrams, machine protection diagrams, failure scenario analysis - Josh, Scot, Mark S
 
* Status of PLC programming - Mark W
 
* Status of PLC programming - Mark W

Revision as of 08:44, 31 March 2010

Solenoid Coil Test Weekly Meeting

Location and Time

  • Thu 1-Apr-2010 9:45am ARC 428


Agenda

  • Safety review and progress towards getting OSP and COO - Elliott, Josh, Tim
    • What is the next step
    • OSP writing assignments and subject matter experts
  • Progress concerning EWEB module, HMI programming, UPS, terminal server, etc. - Elliott, Yi
  • EPICS connection to PLC - Elliott
  • P&I and wiring diagrams, machine protection diagrams, failure scenario analysis - Josh, Scot, Mark S
  • Status of PLC programming - Mark W
  • Progress towards testing PLC program in 101 and F117 - Mark W, Scot, Mark S
  • What PLC display pages are needed (HMI and web) - Josh
  • Wiring progress in F117 - Scot
  • Installation progress - Tom
  • Tying into existing vent piping system - Tom
  • Status of all parts orders - George
  • Coil 1 repair status - George
  • Coil 2 repair status - George
  • Coil 3 progress at IUCF - George
  • Coil 4 controls wiring replacement - George
  • 5 G contours - George