Difference between revisions of "Coil Test Weekly Meeting 14-Jan-2010"
From GlueXWiki
m |
m |
||
Line 19: | Line 19: | ||
* Coil 1 cryostat testing status - George | * Coil 1 cryostat testing status - George | ||
* Construction/installation sequence drawings - George | * Construction/installation sequence drawings - George | ||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
* Status of interface to cryo can - George | * Status of interface to cryo can - George | ||
* Status of pressure relief system design - George | * Status of pressure relief system design - George | ||
Line 33: | Line 26: | ||
* Coil 4 controls wiring replacement - George | * Coil 4 controls wiring replacement - George | ||
* Shipping rails and transportainer from IUCF - Chuck | * Shipping rails and transportainer from IUCF - Chuck | ||
+ | * Arrange for electrical work in Test Lab - Tom | ||
+ | * Arrange for telecom in Test Lab - Elliott | ||
+ | * Arrange for networking in Test Lab - Elliott | ||
+ | * GN2 vent piping system - Tom | ||
+ | * QWeak area, bigger door in F117 - Tom | ||
+ | * Locating computer in SRF control room - Elliott | ||
+ | * Backup computer - Elliott | ||
* Safety reviews: when to start formal process - George, Elliott | * Safety reviews: when to start formal process - George, Elliott | ||
* 5 G contours - George | * 5 G contours - George | ||
* Coil Test [[Solenoid_Coil_Test | Top To-Do items]] | * Coil Test [[Solenoid_Coil_Test | Top To-Do items]] |
Revision as of 11:56, 11 January 2010
Solenoid Coil Test Weekly Meeting
Location and Time
- Thu 14-Jan-2010 9:45 am ARC 428
Agenda
- Status of PLC programming - Mark W
- A-B EWEB module for web access (example page)- Elliott
- Power narrative to Mark W - George
- Finalizing P&I diagram - George, Elliott
- What controls equipment still hasn't arrived - Scot
- Wiring progress in F117 - Scot
- FastTrack schedule status - George, Chuck
- Status of controls drawings and wiring lists - Scot
- Coil 1 cryostat testing status - George
- Construction/installation sequence drawings - George
- Status of interface to cryo can - George
- Status of pressure relief system design - George
- Coil 1 modification and testing - George
- Coil 2 cost and schedule - George
- Coil 3 statement of work, visit and IUCF contract - George, Tom
- Coil 4 controls wiring replacement - George
- Shipping rails and transportainer from IUCF - Chuck
- Arrange for electrical work in Test Lab - Tom
- Arrange for telecom in Test Lab - Elliott
- Arrange for networking in Test Lab - Elliott
- GN2 vent piping system - Tom
- QWeak area, bigger door in F117 - Tom
- Locating computer in SRF control room - Elliott
- Backup computer - Elliott
- Safety reviews: when to start formal process - George, Elliott
- 5 G contours - George
- Coil Test Top To-Do items