Line 10: Line 10:
  
 
* FastTrack schedule status - George, Chuck
 
* FastTrack schedule status - George, Chuck
* QWeak area, bigger door in F117 - Tom
+
* Status of PLC programming - Mark W
 +
** PhaseManager
 +
** Storing program in XML
 +
** Alarming, paging, email
 
* Moving power supply dump resistor - Mark S
 
* Moving power supply dump resistor - Mark S
 
* Ethernet vs ControlNet and A-B Point I/O order - Elliott
 
* Ethernet vs ControlNet and A-B Point I/O order - Elliott
 +
* QWeak area, bigger door in F117 - Tom
 +
* Two coils per A-B chassis? - Scot
 +
* Ordering remaining controls instrumentation and components - Scot, Elliott
 
* Wiring progress in F117 - Scot
 
* Wiring progress in F117 - Scot
 
* Status of interface to cryo can - George
 
* Status of interface to cryo can - George
 
* Status of pressure relief system design - George
 
* Status of pressure relief system design - George
 
* Status of ordering cryo can - George
 
* Status of ordering cryo can - George
* Ordering remaining controls instrumentation and components - Scot, Elliott
 
* PLC programming and testing - Mark W
 
 
* Coil 1 modification and testing - George
 
* Coil 1 modification and testing - George
 
* Coil 2 cost and schedule - George
 
* Coil 2 cost and schedule - George

Latest revision as of 18:03, 16 December 2009

Solenoid Coil Test Weekly Meeting

Location and Time

  • Thu 17-Dec-2009 9:45 am ARC 428


Agenda

  • FastTrack schedule status - George, Chuck
  • Status of PLC programming - Mark W
    • PhaseManager
    • Storing program in XML
    • Alarming, paging, email
  • Moving power supply dump resistor - Mark S
  • Ethernet vs ControlNet and A-B Point I/O order - Elliott
  • QWeak area, bigger door in F117 - Tom
  • Two coils per A-B chassis? - Scot
  • Ordering remaining controls instrumentation and components - Scot, Elliott
  • Wiring progress in F117 - Scot
  • Status of interface to cryo can - George
  • Status of pressure relief system design - George
  • Status of ordering cryo can - George
  • Coil 1 modification and testing - George
  • Coil 2 cost and schedule - George
  • Coil 3 statement of work, visit and IUCF contract - George, Tom
  • Coil 4 controls wiring replacement - George
  • Shipping rails and transportainer from IUCF - Chuck
  • Safety reviews: when to start formal process - George, Elliott
  • 5 G contours - George
  • Coil Test Top To-Do items