Difference between revisions of "JEF meeting, October 25, 2024"

From GlueXWiki
Jump to: navigation, search
(Connection)
 
Line 5: Line 5:
 
* [https://halldweb.jlab.org/wiki-private/index.php/JEF_Weekly_Meeting#Connection_information Connection information]
 
* [https://halldweb.jlab.org/wiki-private/index.php/JEF_Weekly_Meeting#Connection_information Connection information]
  
 +
= Agenda =
 
'''Preparation of parts for ECAL''' -- Sasha  
 
'''Preparation of parts for ECAL''' -- Sasha  
 
* - HV distribution boards  [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/hv_board1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/hv_board2.jpg]
 
* - HV distribution boards  [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/hv_board1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/hv_board2.jpg]
Line 49: Line 50:
 
::  Conference trip was not supported by Hall D
 
::  Conference trip was not supported by Hall D
  
= Agenda =
+
=Minutes=
 
+
Attendees: Bill, Igal, Sasha, Laveen, Jane, Olga, Phil, Liping, Zhikun, Vlad, S.T.
*'''Preparation of parts for ECAL''' -- Sasha
+
* Receive 2 temporary HV distribution boards (holes needed to be redone, but now okay)
*'''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha, All
+
** Cables all assembled for these 2, 3rd bundle done ready to use when 3rd board available
*'''Restoring PS test setup''' [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/ps_setup.jpg]
+
** Order for final boards out, expect delivery some time in November
*''' [https://halldweb.jlab.org/wiki/index.php/ECAL_Commissioning ECAL commissioning]''' -- Sasha, All
+
** Used to check HV interlocks -- working!
*'''Calibrations'''
+
* Working on increasing light output for LMS
*'''Analysis/Simulation'''
+
** New board with 9 LEDs with smaller aperture, shine light directly on fibers
 +
*Laveen to work on reference PMT effort
 +
*Added another pair of scintillators for cosmic ray setup (one above FCAL, one below)
 +
** Covering ECAL and FCAL blocks
 +
** Cables need to be connected
 +
* Cooling/environment control
 +
** 2 chillers ready, circulating coolant
 +
** Waiting for dehumidifier
 +
** Fan installed in dark room to blow cold air on insert
 +
** Will add more sensors
 +
* DAQ
 +
** Read out ECAL scalers using LMS trigger at 500 Hz
 +
*** Not EPICS yet
 +
*** Some problem channels identified
 +
** Baseline (pedestal) calibration
 +
** Test with 3 out of 7 crates
 +
* Schedule held up by missing HV boards -- now ready by mid December?
 +
** When arrive expect need another week for installation
 +
** Some time needed to check HV control via EPICS
 +
* Calibration:  plan to start with cosmics, then real data (Compton, Pi0)

Latest revision as of 13:13, 28 October 2024

Connection

Meeting time and location:

Agenda

Preparation of parts for ECAL -- Sasha

  • - HV distribution boards [1][2]
- Connectors and cables were installed on the PCBs of 2 HV distribution boards. Sammy and Chris are working on the third board, it will likely be ready during next week (Sammy also works on GEM/TRD)
- Boxes for HV boards have been just been ordered. Expected delivery date 11/15/2024.
- Vince P. has machined parts for two temporary distribution boards. Two temporary HV distribution boards were assembled. The holes for connectors were too narrow, the tech group fixed it.
- Have received all parts for the new version of the LMS light source

Installation of the FCAL2 detector & integration to GlueX -- Sasha, All

  • Installation of the light distribution board of the ECAL LMS [3]
- Vlad P. has slightly modified the design of the LMS light source in order to increase the amount of light. Chris S. is working on a new board with 9 LEDs.
  • Implementing ECAL into the GlueX DAQ [4]
- rocecal3 crate was fixed [5] (initial DAQ implementation [6])
- implementing flash ADC scalers [7][8]
- translation table for the ECAL (finalize/check translation DB, generate xml file, import to the CCDB) - done [9]
- implementing and verifying ECAL LMS trigger [10]
- implementing and verifying the ECAL physics trigger. First event reconstructed using the GlueX software [11]
- Start implementing VTP trigger modules. Requires modification of firmware. The trigger crates may be unavailable for 1 - 1.5 months.
- The VTP was installed in the D2-1-TOP crate, IP address assigned, and can be booted now
- Connecting cooling pipes to the ECAL fan (done by tech group)
- Installing dark room ceiling and insulation inside the room, required for cooling test (almost complete)
- Test cooling system (in progress, almost complete)
- Installing HV distribution boards, start switching the detector ON (waiting for HV boxes)

Restoring PS test setup [20]

ECAL commissioning -- Sasha, All

Calibrations

Analysis/Simulation

Laveen Update

Presentation at IEEE [21]

Conference trip was not supported by Hall D

Minutes

Attendees: Bill, Igal, Sasha, Laveen, Jane, Olga, Phil, Liping, Zhikun, Vlad, S.T.

  • Receive 2 temporary HV distribution boards (holes needed to be redone, but now okay)
    • Cables all assembled for these 2, 3rd bundle done ready to use when 3rd board available
    • Order for final boards out, expect delivery some time in November
    • Used to check HV interlocks -- working!
  • Working on increasing light output for LMS
    • New board with 9 LEDs with smaller aperture, shine light directly on fibers
  • Laveen to work on reference PMT effort
  • Added another pair of scintillators for cosmic ray setup (one above FCAL, one below)
    • Covering ECAL and FCAL blocks
    • Cables need to be connected
  • Cooling/environment control
    • 2 chillers ready, circulating coolant
    • Waiting for dehumidifier
    • Fan installed in dark room to blow cold air on insert
    • Will add more sensors
  • DAQ
    • Read out ECAL scalers using LMS trigger at 500 Hz
      • Not EPICS yet
      • Some problem channels identified
    • Baseline (pedestal) calibration
    • Test with 3 out of 7 crates
  • Schedule held up by missing HV boards -- now ready by mid December?
    • When arrive expect need another week for installation
    • Some time needed to check HV control via EPICS
  • Calibration: plan to start with cosmics, then real data (Compton, Pi0)