= Agenda =
 
'''Preparation of parts for ECAL''' -- Sasha  
 
'''Preparation of parts for ECAL''' -- Sasha  
 
* - HV distribution boards  [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/hv_board1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/hv_board2.jpg]
 
* - HV distribution boards  [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/hv_board1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/hv_board2.jpg]
 
::  - Connectors and cables were installed on the PCBs of 2 HV distribution boards. Sammy and Chris are working on the third board, it will likely be ready during next week (Sammy also works on GEM/TRD)
 
::  - Connectors and cables were installed on the PCBs of 2 HV distribution boards. Sammy and Chris are working on the third board, it will likely be ready during next week (Sammy also works on GEM/TRD)
 
::  - Boxes for HV boards have been just been ordered. Expected delivery date 11/15/2024.
 
::  - Boxes for HV boards have been just been ordered. Expected delivery date 11/15/2024.
::  - Vince P. has machined parts for two temporary distribution boards. They should be assembled either today or in the beginning of next week.
+
::  - Vince P. has machined parts for two temporary distribution boards. Two temporary HV distribution boards were assembled. The holes for connectors were too narrow, the tech group fixed it.
::  - Ordered parts (LEDs and components) for the updated LMS light source.
+
::  - Have received all parts for the new version of the LMS light source  
 
'''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha, All
 
'''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha, All
 
* Installation of the light distribution board of the ECAL LMS [https://logbooks.jlab.org/entry/4317207]
 
* Installation of the light distribution board of the ECAL LMS [https://logbooks.jlab.org/entry/4317207]
::  - Vlad P. has slightly modified the design of the LMS light source in order to increase the amount of light. We'll start tested the new version during next or following week.
+
::  - Vlad P. has slightly modified the design of the LMS light source in order to increase the amount of light. Chris S. is working on a new board with 9 LEDs.  
 
* Implementing ECAL into the GlueX DAQ [https://logbooks.jlab.org/entry/4316928]
 
* Implementing ECAL into the GlueX DAQ [https://logbooks.jlab.org/entry/4316928]
 
:: - rocecal3 crate was fixed [https://logbooks.jlab.org/entry/4317415] (initial DAQ implementation [https://logbooks.jlab.org/entry/4316928])
 
:: - rocecal3 crate was fixed [https://logbooks.jlab.org/entry/4317415] (initial DAQ implementation [https://logbooks.jlab.org/entry/4316928])
:: - implementing flash ADC scalers [https://logbooks.jlab.org/entry/4319280]
+
:: - implementing flash ADC scalers [https://logbooks.jlab.org/entry/4319280][https://logbooks.jlab.org/entry/4319672]
 
:: - translation table for the ECAL (finalize/check translation DB, generate xml file, import to the CCDB) - done [https://logbooks.jlab.org/entry/4317904]
 
:: - translation table for the ECAL (finalize/check translation DB, generate xml file, import to the CCDB) - done [https://logbooks.jlab.org/entry/4317904]
 
:: - implementing and verifying ECAL LMS trigger [https://logbooks.jlab.org/entry/4317903]
 
:: - implementing and verifying ECAL LMS trigger [https://logbooks.jlab.org/entry/4317903]
Line 28: Line 29:
 
* [https://halldweb.jlab.org/detectors/fcal2/installation/safety_docs/safety.jpg Safety briefings] - Vlad, Sasha
 
* [https://halldweb.jlab.org/detectors/fcal2/installation/safety_docs/safety.jpg Safety briefings] - Vlad, Sasha
 
* [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page]
 
* [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page]
* Installation of temporary HV distribution boards and testing flash ADC scalers [https://logbooks.jlab.org/entry/4319280]
+
* Installation of temporary HV distribution boards and testing flash ADC scalers [https://logbooks.jlab.org/entry/4319280][https://logbooks.jlab.org/entry/4319672]
 
* [https://halldweb.jlab.org/wiki/index.php/FCAL2_Meetings FCAL2 Engineering Meetings]
 
* [https://halldweb.jlab.org/wiki/index.php/FCAL2_Meetings FCAL2 Engineering Meetings]
 
* Remaining installation tasks
 
* Remaining installation tasks
Line 49: Line 50:
 
::  Conference trip was not supported by Hall D
 
::  Conference trip was not supported by Hall D
  
= Agenda =
+
=Minutes=
 
+
Attendees: Bill, Igal, Sasha, Laveen, Jane, Olga, Phil, Liping, Zhikun, Vlad, S.T.
*'''Preparation of parts for ECAL''' -- Sasha
+
* Receive 2 temporary HV distribution boards (holes needed to be redone, but now okay)
*'''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha, All
+
** Cables all assembled for these 2, 3rd bundle done ready to use when 3rd board available
*'''Restoring PS test setup''' [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/ps_setup.jpg]
+
** Order for final boards out, expect delivery some time in November
*''' [https://halldweb.jlab.org/wiki/index.php/ECAL_Commissioning ECAL commissioning]''' -- Sasha, All
+
** Used to check HV interlocks -- working!
*'''Calibrations'''
+
* Working on increasing light output for LMS
*'''Analysis/Simulation'''
+
** New board with 9 LEDs with smaller aperture, shine light directly on fibers
 +
*Laveen to work on reference PMT effort
 +
*Added another pair of scintillators for cosmic ray setup (one above FCAL, one below)
 +
** Covering ECAL and FCAL blocks
 +
** Cables need to be connected
 +
* Cooling/environment control
 +
** 2 chillers ready, circulating coolant
 +
** Waiting for dehumidifier
 +
** Fan installed in dark room to blow cold air on insert
 +
** Will add more sensors
 +
* DAQ
 +
** Read out ECAL scalers using LMS trigger at 500 Hz
 +
*** Not EPICS yet
 +
*** Some problem channels identified
 +
** Baseline (pedestal) calibration
 +
** Test with 3 out of 7 crates
 +
* Schedule held up by missing HV boards -- now ready by mid December?
 +
** When arrive expect need another week for installation
 +
** Some time needed to check HV control via EPICS
 +
* Calibration:  plan to start with cosmics, then real data (Compton, Pi0)

Latest revision as of 13:13, 28 October 2024

Connection

Meeting time and location:

Agenda

Preparation of parts for ECAL -- Sasha

  • - HV distribution boards [1][2]
- Connectors and cables were installed on the PCBs of 2 HV distribution boards. Sammy and Chris are working on the third board, it will likely be ready during next week (Sammy also works on GEM/TRD)
- Boxes for HV boards have been just been ordered. Expected delivery date 11/15/2024.
- Vince P. has machined parts for two temporary distribution boards. Two temporary HV distribution boards were assembled. The holes for connectors were too narrow, the tech group fixed it.
- Have received all parts for the new version of the LMS light source

Installation of the FCAL2 detector & integration to GlueX -- Sasha, All

  • Installation of the light distribution board of the ECAL LMS [3]
- Vlad P. has slightly modified the design of the LMS light source in order to increase the amount of light. Chris S. is working on a new board with 9 LEDs.
  • Implementing ECAL into the GlueX DAQ [4]
- rocecal3 crate was fixed [5] (initial DAQ implementation [6])
- implementing flash ADC scalers [7][8]
- translation table for the ECAL (finalize/check translation DB, generate xml file, import to the CCDB) - done [9]
- implementing and verifying ECAL LMS trigger [10]
- implementing and verifying the ECAL physics trigger. First event reconstructed using the GlueX software [11]
- Start implementing VTP trigger modules. Requires modification of firmware. The trigger crates may be unavailable for 1 - 1.5 months.
- The VTP was installed in the D2-1-TOP crate, IP address assigned, and can be booted now
- Connecting cooling pipes to the ECAL fan (done by tech group)
- Installing dark room ceiling and insulation inside the room, required for cooling test (almost complete)
- Test cooling system (in progress, almost complete)
- Installing HV distribution boards, start switching the detector ON (waiting for HV boxes)

Restoring PS test setup [20]

ECAL commissioning -- Sasha, All

Calibrations

Analysis/Simulation

Laveen Update

Presentation at IEEE [21]

Conference trip was not supported by Hall D

Minutes

Attendees: Bill, Igal, Sasha, Laveen, Jane, Olga, Phil, Liping, Zhikun, Vlad, S.T.

  • Receive 2 temporary HV distribution boards (holes needed to be redone, but now okay)
    • Cables all assembled for these 2, 3rd bundle done ready to use when 3rd board available
    • Order for final boards out, expect delivery some time in November
    • Used to check HV interlocks -- working!
  • Working on increasing light output for LMS
    • New board with 9 LEDs with smaller aperture, shine light directly on fibers
  • Laveen to work on reference PMT effort
  • Added another pair of scintillators for cosmic ray setup (one above FCAL, one below)
    • Covering ECAL and FCAL blocks
    • Cables need to be connected
  • Cooling/environment control
    • 2 chillers ready, circulating coolant
    • Waiting for dehumidifier
    • Fan installed in dark room to blow cold air on insert
    • Will add more sensors
  • DAQ
    • Read out ECAL scalers using LMS trigger at 500 Hz
      • Not EPICS yet
      • Some problem channels identified
    • Baseline (pedestal) calibration
    • Test with 3 out of 7 crates
  • Schedule held up by missing HV boards -- now ready by mid December?
    • When arrive expect need another week for installation
    • Some time needed to check HV control via EPICS
  • Calibration: plan to start with cosmics, then real data (Compton, Pi0)