Difference between revisions of "JEF meeting, October 25, 2024"
From GlueXWiki
(→Connection) |
|||
(8 intermediate revisions by one other user not shown) | |||
Line 5: | Line 5: | ||
* [https://halldweb.jlab.org/wiki-private/index.php/JEF_Weekly_Meeting#Connection_information Connection information] | * [https://halldweb.jlab.org/wiki-private/index.php/JEF_Weekly_Meeting#Connection_information Connection information] | ||
+ | = Agenda = | ||
'''Preparation of parts for ECAL''' -- Sasha | '''Preparation of parts for ECAL''' -- Sasha | ||
* - HV distribution boards [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/hv_board1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/hv_board2.jpg] | * - HV distribution boards [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/hv_board1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/hv_board2.jpg] | ||
:: - Connectors and cables were installed on the PCBs of 2 HV distribution boards. Sammy and Chris are working on the third board, it will likely be ready during next week (Sammy also works on GEM/TRD) | :: - Connectors and cables were installed on the PCBs of 2 HV distribution boards. Sammy and Chris are working on the third board, it will likely be ready during next week (Sammy also works on GEM/TRD) | ||
:: - Boxes for HV boards have been just been ordered. Expected delivery date 11/15/2024. | :: - Boxes for HV boards have been just been ordered. Expected delivery date 11/15/2024. | ||
− | :: - Vince P. has machined parts for two temporary distribution boards. | + | :: - Vince P. has machined parts for two temporary distribution boards. Two temporary HV distribution boards were assembled. The holes for connectors were too narrow, the tech group fixed it. |
− | :: - | + | :: - Have received all parts for the new version of the LMS light source |
'''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha, All | '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha, All | ||
* Installation of the light distribution board of the ECAL LMS [https://logbooks.jlab.org/entry/4317207] | * Installation of the light distribution board of the ECAL LMS [https://logbooks.jlab.org/entry/4317207] | ||
− | :: - Vlad P. has slightly modified the design of the LMS light source in order to increase the amount of light. | + | :: - Vlad P. has slightly modified the design of the LMS light source in order to increase the amount of light. Chris S. is working on a new board with 9 LEDs. |
* Implementing ECAL into the GlueX DAQ [https://logbooks.jlab.org/entry/4316928] | * Implementing ECAL into the GlueX DAQ [https://logbooks.jlab.org/entry/4316928] | ||
:: - rocecal3 crate was fixed [https://logbooks.jlab.org/entry/4317415] (initial DAQ implementation [https://logbooks.jlab.org/entry/4316928]) | :: - rocecal3 crate was fixed [https://logbooks.jlab.org/entry/4317415] (initial DAQ implementation [https://logbooks.jlab.org/entry/4316928]) | ||
− | :: - implementing flash ADC scalers [https://logbooks.jlab.org/entry/ | + | :: - implementing flash ADC scalers [https://logbooks.jlab.org/entry/4319280][https://logbooks.jlab.org/entry/4319672] |
:: - translation table for the ECAL (finalize/check translation DB, generate xml file, import to the CCDB) - done [https://logbooks.jlab.org/entry/4317904] | :: - translation table for the ECAL (finalize/check translation DB, generate xml file, import to the CCDB) - done [https://logbooks.jlab.org/entry/4317904] | ||
:: - implementing and verifying ECAL LMS trigger [https://logbooks.jlab.org/entry/4317903] | :: - implementing and verifying ECAL LMS trigger [https://logbooks.jlab.org/entry/4317903] | ||
Line 22: | Line 23: | ||
:: - Start implementing VTP trigger modules. Requires modification of firmware. <span style="color:red"> The trigger crates may be unavailable for 1 - 1.5 months.</span> | :: - Start implementing VTP trigger modules. Requires modification of firmware. <span style="color:red"> The trigger crates may be unavailable for 1 - 1.5 months.</span> | ||
::: - The VTP was installed in the D2-1-TOP crate, IP address assigned, and can be booted now | ::: - The VTP was installed in the D2-1-TOP crate, IP address assigned, and can be booted now | ||
− | * Installation of scintillating paddles for cosmic tests [https://logbooks.jlab.org/entry/4317905] [https://logbooks.jlab.org/entry/4318834] | + | * Installation of scintillating paddles for cosmic tests [https://logbooks.jlab.org/entry/4317905] [https://logbooks.jlab.org/entry/4318834][https://logbooks.jlab.org/entry/4319535] |
* ECAL HV interlock check [https://logbooks.jlab.org/entry/4318704] | * ECAL HV interlock check [https://logbooks.jlab.org/entry/4318704] | ||
* Cable map of the ECAL LG modules after installing ECAL [https://logbooks.jlab.org/entry/4318588] | * Cable map of the ECAL LG modules after installing ECAL [https://logbooks.jlab.org/entry/4318588] | ||
Line 28: | Line 29: | ||
* [https://halldweb.jlab.org/detectors/fcal2/installation/safety_docs/safety.jpg Safety briefings] - Vlad, Sasha | * [https://halldweb.jlab.org/detectors/fcal2/installation/safety_docs/safety.jpg Safety briefings] - Vlad, Sasha | ||
* [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page] | * [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page] | ||
+ | * Installation of temporary HV distribution boards and testing flash ADC scalers [https://logbooks.jlab.org/entry/4319280][https://logbooks.jlab.org/entry/4319672] | ||
* [https://halldweb.jlab.org/wiki/index.php/FCAL2_Meetings FCAL2 Engineering Meetings] | * [https://halldweb.jlab.org/wiki/index.php/FCAL2_Meetings FCAL2 Engineering Meetings] | ||
* Remaining installation tasks | * Remaining installation tasks | ||
Line 48: | Line 50: | ||
:: Conference trip was not supported by Hall D | :: Conference trip was not supported by Hall D | ||
− | = | + | =Minutes= |
− | + | Attendees: Bill, Igal, Sasha, Laveen, Jane, Olga, Phil, Liping, Zhikun, Vlad, S.T. | |
− | * | + | * Receive 2 temporary HV distribution boards (holes needed to be redone, but now okay) |
− | * | + | ** Cables all assembled for these 2, 3rd bundle done ready to use when 3rd board available |
− | * | + | ** Order for final boards out, expect delivery some time in November |
− | * | + | ** Used to check HV interlocks -- working! |
− | * | + | * Working on increasing light output for LMS |
− | * | + | ** New board with 9 LEDs with smaller aperture, shine light directly on fibers |
+ | *Laveen to work on reference PMT effort | ||
+ | *Added another pair of scintillators for cosmic ray setup (one above FCAL, one below) | ||
+ | ** Covering ECAL and FCAL blocks | ||
+ | ** Cables need to be connected | ||
+ | * Cooling/environment control | ||
+ | ** 2 chillers ready, circulating coolant | ||
+ | ** Waiting for dehumidifier | ||
+ | ** Fan installed in dark room to blow cold air on insert | ||
+ | ** Will add more sensors | ||
+ | * DAQ | ||
+ | ** Read out ECAL scalers using LMS trigger at 500 Hz | ||
+ | *** Not EPICS yet | ||
+ | *** Some problem channels identified | ||
+ | ** Baseline (pedestal) calibration | ||
+ | ** Test with 3 out of 7 crates | ||
+ | * Schedule held up by missing HV boards -- now ready by mid December? | ||
+ | ** When arrive expect need another week for installation | ||
+ | ** Some time needed to check HV control via EPICS | ||
+ | * Calibration: plan to start with cosmics, then real data (Compton, Pi0) |
Latest revision as of 13:13, 28 October 2024
Connection
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
Preparation of parts for ECAL -- Sasha
- - Connectors and cables were installed on the PCBs of 2 HV distribution boards. Sammy and Chris are working on the third board, it will likely be ready during next week (Sammy also works on GEM/TRD)
- - Boxes for HV boards have been just been ordered. Expected delivery date 11/15/2024.
- - Vince P. has machined parts for two temporary distribution boards. Two temporary HV distribution boards were assembled. The holes for connectors were too narrow, the tech group fixed it.
- - Have received all parts for the new version of the LMS light source
Installation of the FCAL2 detector & integration to GlueX -- Sasha, All
- Installation of the light distribution board of the ECAL LMS [3]
- - Vlad P. has slightly modified the design of the LMS light source in order to increase the amount of light. Chris S. is working on a new board with 9 LEDs.
- Implementing ECAL into the GlueX DAQ [4]
- - rocecal3 crate was fixed [5] (initial DAQ implementation [6])
- - implementing flash ADC scalers [7][8]
- - translation table for the ECAL (finalize/check translation DB, generate xml file, import to the CCDB) - done [9]
- - implementing and verifying ECAL LMS trigger [10]
- - implementing and verifying the ECAL physics trigger. First event reconstructed using the GlueX software [11]
- - Start implementing VTP trigger modules. Requires modification of firmware. The trigger crates may be unavailable for 1 - 1.5 months.
- - The VTP was installed in the D2-1-TOP crate, IP address assigned, and can be booted now
- Installation of scintillating paddles for cosmic tests [12] [13][14]
- ECAL HV interlock check [15]
- Cable map of the ECAL LG modules after installing ECAL [16]
- Reinstalling cables on the ECAL LV distribution board [17]
- Safety briefings - Vlad, Sasha
- Detector installation page
- Installation of temporary HV distribution boards and testing flash ADC scalers [18][19]
- FCAL2 Engineering Meetings
- Remaining installation tasks
- - Connecting cooling pipes to the ECAL fan (done by tech group)
- - Installing dark room ceiling and insulation inside the room, required for cooling test (almost complete)
- - Test cooling system (in progress, almost complete)
- - Installing HV distribution boards, start switching the detector ON (waiting for HV boxes)
Restoring PS test setup [20]
ECAL commissioning -- Sasha, All
Calibrations
Analysis/Simulation
Presentation at IEEE [21]
- Conference trip was not supported by Hall D
Minutes
Attendees: Bill, Igal, Sasha, Laveen, Jane, Olga, Phil, Liping, Zhikun, Vlad, S.T.
- Receive 2 temporary HV distribution boards (holes needed to be redone, but now okay)
- Cables all assembled for these 2, 3rd bundle done ready to use when 3rd board available
- Order for final boards out, expect delivery some time in November
- Used to check HV interlocks -- working!
- Working on increasing light output for LMS
- New board with 9 LEDs with smaller aperture, shine light directly on fibers
- Laveen to work on reference PMT effort
- Added another pair of scintillators for cosmic ray setup (one above FCAL, one below)
- Covering ECAL and FCAL blocks
- Cables need to be connected
- Cooling/environment control
- 2 chillers ready, circulating coolant
- Waiting for dehumidifier
- Fan installed in dark room to blow cold air on insert
- Will add more sensors
- DAQ
- Read out ECAL scalers using LMS trigger at 500 Hz
- Not EPICS yet
- Some problem channels identified
- Baseline (pedestal) calibration
- Test with 3 out of 7 crates
- Read out ECAL scalers using LMS trigger at 500 Hz
- Schedule held up by missing HV boards -- now ready by mid December?
- When arrive expect need another week for installation
- Some time needed to check HV control via EPICS
- Calibration: plan to start with cosmics, then real data (Compton, Pi0)