Difference between revisions of "JEF meeting, October 25, 2024"
From GlueXWiki
(→Connection) |
(→Connection) |
||
Line 28: | Line 28: | ||
* [https://halldweb.jlab.org/detectors/fcal2/installation/safety_docs/safety.jpg Safety briefings] - Vlad, Sasha | * [https://halldweb.jlab.org/detectors/fcal2/installation/safety_docs/safety.jpg Safety briefings] - Vlad, Sasha | ||
* [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page] | * [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page] | ||
− | * Installation of temporary HV distribution boards and testing flash ADC scalers [https://logbooks.jlab.org/entry/ | + | * Installation of temporary HV distribution boards and testing flash ADC scalers [https://logbooks.jlab.org/entry/4319280] |
* [https://halldweb.jlab.org/wiki/index.php/FCAL2_Meetings FCAL2 Engineering Meetings] | * [https://halldweb.jlab.org/wiki/index.php/FCAL2_Meetings FCAL2 Engineering Meetings] | ||
* Remaining installation tasks | * Remaining installation tasks |
Revision as of 08:20, 25 October 2024
Connection
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Preparation of parts for ECAL -- Sasha
- - Connectors and cables were installed on the PCBs of 2 HV distribution boards. Sammy and Chris are working on the third board, it will likely be ready during next week (Sammy also works on GEM/TRD)
- - Boxes for HV boards have been just been ordered. Expected delivery date 11/15/2024.
- - Vince P. has machined parts for two temporary distribution boards. They should be assembled either today or in the beginning of next week.
- - Ordered parts (LEDs and components) for the updated LMS light source.
Installation of the FCAL2 detector & integration to GlueX -- Sasha, All
- Installation of the light distribution board of the ECAL LMS [3]
- - Vlad P. has slightly modified the design of the LMS light source in order to increase the amount of light. We'll start tested the new version during next or following week.
- Implementing ECAL into the GlueX DAQ [4]
- - rocecal3 crate was fixed [5] (initial DAQ implementation [6])
- - implementing flash ADC scalers [7]
- - translation table for the ECAL (finalize/check translation DB, generate xml file, import to the CCDB) - done [8]
- - implementing and verifying ECAL LMS trigger [9]
- - implementing and verifying the ECAL physics trigger. First event reconstructed using the GlueX software [10]
- - Start implementing VTP trigger modules. Requires modification of firmware. The trigger crates may be unavailable for 1 - 1.5 months.
- - The VTP was installed in the D2-1-TOP crate, IP address assigned, and can be booted now
- Installation of scintillating paddles for cosmic tests [11] [12][13]
- ECAL HV interlock check [14]
- Cable map of the ECAL LG modules after installing ECAL [15]
- Reinstalling cables on the ECAL LV distribution board [16]
- Safety briefings - Vlad, Sasha
- Detector installation page
- Installation of temporary HV distribution boards and testing flash ADC scalers [17]
- FCAL2 Engineering Meetings
- Remaining installation tasks
- - Connecting cooling pipes to the ECAL fan (done by tech group)
- - Installing dark room ceiling and insulation inside the room, required for cooling test (almost complete)
- - Test cooling system (in progress, almost complete)
- - Installing HV distribution boards, start switching the detector ON (waiting for HV boxes)
Restoring PS test setup [18]
ECAL commissioning -- Sasha, All
Calibrations
Analysis/Simulation
Presentation at IEEE [19]
- Conference trip was not supported by Hall D
Agenda
- Preparation of parts for ECAL -- Sasha
- Installation of the FCAL2 detector & integration to GlueX -- Sasha, All
- Restoring PS test setup [20]
- ECAL commissioning -- Sasha, All
- Calibrations
- Analysis/Simulation