'''Preparation of parts for ECAL''' -- Sasha | '''Preparation of parts for ECAL''' -- Sasha | ||
− | + | * - HV long cable: Sammy and Mindy are finishing up with assembling cables, 2 cables are left | |
− | '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad / Laveen | + | * - HV distribution boards [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/hv_board1.jpg][https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/hv_board2.jpg] |
− | + | :: - 5 (12 x 4) and 5 (6 x 8) boards have been received. Chris checked connections. All remaining PCB boards are expected to be in the lab on Sep 12. | |
+ | :: - Chris is finalizing design of the distribution boxes (each box will comprise 9 PCBs). He expects to submit PR during next week. | ||
+ | * - Fix front panel of two LV distribution boards [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/lv_board1.jpg] | ||
+ | ::: - new plates for the LV distribution boards should arrive today. Need to re-install 2 distribution boards and connect cables | ||
+ | '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad / Hakob / Laveen | ||
+ | * Installation and testing dividers has been completed [https://logbooks.jlab.org/entry/4316213] | ||
+ | :: - need to arrange cables on chains | ||
+ | :: - need to arrange cables on cable trays - done [https://logbooks.jlab.org/entry/4316915] | ||
+ | :: - preparing spare cables (7 short HV, 8 signal and LV) | ||
+ | * Installation of the light distribution board of the ECAL LMS [https://logbooks.jlab.org/entry/4317207] | ||
+ | * Implementing ECAL into the GlueX DAQ [https://logbooks.jlab.org/entry/4316928] | ||
+ | * [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page] | ||
+ | * [https://halldweb.jlab.org/detectors/fcal2/installation/safety_docs/Document_240716_195013-1.pdf Safety briefings] | ||
+ | * Remaining installation tasks | ||
+ | :: - Installing HV distribution boards (start switching the detector ON) | ||
+ | :: - Installing dark room ceiling and insulation inside the room | ||
+ | :: - Checking cooling system | ||
'''Students''' -- Sasha | '''Students''' -- Sasha | ||
− | + | * - Expect one student from Wuhan, waiting for the US visa | |
+ | * [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/lv_board1.jpg Restoring PS test setup] | ||
''' [https://halldweb.jlab.org/wiki/index.php/ECAL_Commissioning ECAL commissioning]''' -- Sasha, All | ''' [https://halldweb.jlab.org/wiki/index.php/ECAL_Commissioning ECAL commissioning]''' -- Sasha, All | ||
− | + | =Minutes= | |
− | + | Attendees: Igal, Laveen, Phil, Liping, Vlad, Sasha, Zisis, Stjepan, Ilya, S.T. | |
− | + | * Waiting for cover panels for two LV boards | |
− | + | * No progress in HV distribution board design | |
− | + | * Cables organized on chains and in cable trays | |
+ | * Installed final version of light distribution board for LMS on integrating sphere | ||
+ | ** Looked at signals on some PMTS, pulses look good, but amplitudes somewhat small | ||
+ | ** Need to increase light 10x | ||
+ | * Sasha implemented DAQ configuration for ECAL crates | ||
+ | ** Optical links work, need to integrate LMS trigger | ||
+ | ** Found faulty controller for ROCECAL3 | ||
+ | * Dark room installation needs to be completed | ||
+ | * Checking of cooling system still needs to be completed before we can turn on the whole detector | ||
+ | * PS setup in the hall in the process of being restored (we can use this to study some small-scale prototypes) | ||
+ | * Started commissioning run plan |
Latest revision as of 10:21, 23 September 2024
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
Preparation of parts for ECAL -- Sasha
- - HV long cable: Sammy and Mindy are finishing up with assembling cables, 2 cables are left
- - HV distribution boards [1][2]
- - 5 (12 x 4) and 5 (6 x 8) boards have been received. Chris checked connections. All remaining PCB boards are expected to be in the lab on Sep 12.
- - Chris is finalizing design of the distribution boxes (each box will comprise 9 PCBs). He expects to submit PR during next week.
- - Fix front panel of two LV distribution boards [3]
- - new plates for the LV distribution boards should arrive today. Need to re-install 2 distribution boards and connect cables
Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob / Laveen
- Installation and testing dividers has been completed [4]
- - need to arrange cables on chains
- - need to arrange cables on cable trays - done [5]
- - preparing spare cables (7 short HV, 8 signal and LV)
- Installation of the light distribution board of the ECAL LMS [6]
- Implementing ECAL into the GlueX DAQ [7]
- Detector installation page
- Safety briefings
- Remaining installation tasks
- - Installing HV distribution boards (start switching the detector ON)
- - Installing dark room ceiling and insulation inside the room
- - Checking cooling system
Students -- Sasha
- - Expect one student from Wuhan, waiting for the US visa
- Restoring PS test setup
ECAL commissioning -- Sasha, All
Minutes
Attendees: Igal, Laveen, Phil, Liping, Vlad, Sasha, Zisis, Stjepan, Ilya, S.T.
- Waiting for cover panels for two LV boards
- No progress in HV distribution board design
- Cables organized on chains and in cable trays
- Installed final version of light distribution board for LMS on integrating sphere
- Looked at signals on some PMTS, pulses look good, but amplitudes somewhat small
- Need to increase light 10x
- Sasha implemented DAQ configuration for ECAL crates
- Optical links work, need to integrate LMS trigger
- Found faulty controller for ROCECAL3
- Dark room installation needs to be completed
- Checking of cooling system still needs to be completed before we can turn on the whole detector
- PS setup in the hall in the process of being restored (we can use this to study some small-scale prototypes)
- Started commissioning run plan