Line 13: | Line 13: | ||
* - Fix front panel of two LV distribution boards [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/lv_board1.jpg] | * - Fix front panel of two LV distribution boards [https://halldweb.jlab.org/detectors/fcal2/installation/meetings/08_09_2024/lv_board1.jpg] | ||
::: - new plates for the LV distribution boards should arrive to JLab during next week. Need to re-install 2 distribution boards and connect cables | ::: - new plates for the LV distribution boards should arrive to JLab during next week. Need to re-install 2 distribution boards and connect cables | ||
− | |||
'''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad / Hakob / Laveen | '''Installation of the FCAL2 detector & integration to GlueX''' -- Sasha / Vlad / Hakob / Laveen | ||
* Installation and testing dividers has been completed [https://logbooks.jlab.org/entry/4316213] | * Installation and testing dividers has been completed [https://logbooks.jlab.org/entry/4316213] |
Revision as of 09:10, 20 September 2024
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
Preparation of parts for ECAL -- Sasha
- - HV long cable: Sammy and Mindy are finishing up with assembling cables, 2 cables are left
- - HV distribution boards [1][2]
- - 5 (12 x 4) and 5 (6 x 8) boards have been received. Chris checked connections. All remaining PCB boards are expected to be in the lab on Sep 12.
- - Chris is finalizing design of the distribution boxes (each box will comprise 9 PCBs). He expects to submit PR during next week.
- - Fix front panel of two LV distribution boards [3]
- - new plates for the LV distribution boards should arrive to JLab during next week. Need to re-install 2 distribution boards and connect cables
Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob / Laveen
- Installation and testing dividers has been completed [4]
- - need to arrange cables on chains
- - need to arrange cables on cable trays - done [5]
- - preparing spare cables (7 short HV, 8 signal and LV)
- Installation of the light distribution board of the ECAL LMS [6]
- Implementing ECAL into the GlueX DAQ [7]
- Detector installation page
- Safety briefings
Students -- Sasha
- - Expect one student from Wuhan, waiting for the US visa
ECAL commissioning -- Sasha, All