Difference between revisions of "JEF meeting, September 20, 2024"
From GlueXWiki
(→Agenda) |
(→Agenda) |
||
Line 20: | Line 20: | ||
:: - preparing spare cables (7 short HV, 8 signal and LV) | :: - preparing spare cables (7 short HV, 8 signal and LV) | ||
* Installation of the light distribution board of the ECAL LMS [https://logbooks.jlab.org/entry/4317207] | * Installation of the light distribution board of the ECAL LMS [https://logbooks.jlab.org/entry/4317207] | ||
− | * Implementing ECAL into the GlueX DAQ | + | * Implementing ECAL into the GlueX DAQ [https://logbooks.jlab.org/entry/4316928] |
* [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page] | * [https://halldweb.jlab.org/wiki/index.php/FCAL_Installation Detector installation page] | ||
* [https://halldweb.jlab.org/detectors/fcal2/installation/safety_docs/Document_240716_195013-1.pdf Safety briefings] | * [https://halldweb.jlab.org/detectors/fcal2/installation/safety_docs/Document_240716_195013-1.pdf Safety briefings] |
Revision as of 09:10, 20 September 2024
Meeting time and location:
- 9:30 am EST (JLab time) remote only
- Connection information
Agenda
Preparation of parts for ECAL -- Sasha
- - HV long cable: Sammy and Mindy are finishing up with assembling cables, 2 cables are left
- - HV distribution boards [1][2]
- - 5 (12 x 4) and 5 (6 x 8) boards have been received. Chris checked connections. All remaining PCB boards are expected to be in the lab on Sep 12.
- - Chris is finalizing design of the distribution boxes (each box will comprise 9 PCBs). He expects to submit PR during next week.
- - Fix front panel of two LV distribution boards [3]
- - new plates for the LV distribution boards should arrive to JLab during next week. Need to re-install 2 distribution boards and connect cables
- - LED: Started testing the prototype of the LMS (need to make the detector room light tight)
Installation of the FCAL2 detector & integration to GlueX -- Sasha / Vlad / Hakob / Laveen
- Installation and testing dividers has been completed [4]
- - need to arrange cables on chains
- - need to arrange cables on cable trays - done [5]
- - preparing spare cables (7 short HV, 8 signal and LV)
- Installation of the light distribution board of the ECAL LMS [6]
- Implementing ECAL into the GlueX DAQ [7]
- Detector installation page
- Safety briefings
Students -- Sasha
- - Expect one student from Wuhan, waiting for the US visa
ECAL commissioning -- Sasha, All