− | [[Commissioning run plan]] | + | * [[Commissioning run plan]] |
+ | |||
+ | |||
+ | * DAQ configuration [https://logbooks.jlab.org/entry/4316928] | ||
+ | |||
+ | * Tests with the LMS | ||
+ | |||
+ | * Cosmic tests | ||
+ | :: initial gain calibration | ||
+ | |||
+ | * HV settings |
Latest revision as of 15:05, 16 September 2024
- DAQ configuration [1]
- Tests with the LMS
- Cosmic tests
- initial gain calibration
- HV settings