Difference between revisions of "Run Planning Meeting Notes, August 3- August 10, 2022"
From GlueXWiki
(→Wednesday August 3) |
|||
Line 10: | Line 10: | ||
− | = | + | = Friday August 5 = |
+ | === Past 24 hours === | ||
+ | * Running on empty target (60 nA). | ||
+ | * Plan to do TAC run Thursday was postponed (Today, or around Aug. 15th). | ||
+ | * Everything is going well: 15.1h of ABU (63% efficiency). Time loss mostly due to thunderstorm. | ||
+ | === Shift Reports === | ||
+ | * [https://logbooks.jlab.org/entry/4024235 Day shift summary ] | ||
+ | * [https://logbooks.jlab.org/entry/4024338 Swing shift summary] | ||
+ | * [https://logbooks.jlab.org/entry/4024448 Owl shift summary] | ||
+ | * [https://logbooks.jlab.org/entry/4024539 Early Riser shift summary] | ||
+ | === Reports === | ||
+ | * | ||
+ | * | ||
+ | === Issues === | ||
+ | * Hot wire number 40 for FMWPC Occupancy Layer 1 | ||
+ | |||
+ | === Plans === | ||
+ | * RF recovery until ~11:30am. Access to put back Pb target if no TAC run today? | ||
+ | * TAC run in the afternoon ? (Thunderstorms forecast) or production on Pb. | ||
+ | * Monday day: 5 -> 4 pass change for Hall C (Around 4h. Mostly invasive). | ||
+ | |||
+ | = Thursday August 4 = | ||
=== Past 24 hours === | === Past 24 hours === | ||
* Running on empty target (60 nA). Everything is going nicely and smoothly: 16.6h of ABU (69% efficiency). | * Running on empty target (60 nA). Everything is going nicely and smoothly: 16.6h of ABU (69% efficiency). |
Revision as of 07:24, 5 August 2022
Back to Run Coordination Meetings:Summer2022
Meeting are via ZoomGov: connect (Meeting ID: 160 199 0060 / Passcode 8394)
Hall D counting room white board
Contents
Friday August 5
Past 24 hours
- Running on empty target (60 nA).
- Plan to do TAC run Thursday was postponed (Today, or around Aug. 15th).
- Everything is going well: 15.1h of ABU (63% efficiency). Time loss mostly due to thunderstorm.
Shift Reports
Reports
Issues
- Hot wire number 40 for FMWPC Occupancy Layer 1
Plans
- RF recovery until ~11:30am. Access to put back Pb target if no TAC run today?
- TAC run in the afternoon ? (Thunderstorms forecast) or production on Pb.
- Monday day: 5 -> 4 pass change for Hall C (Around 4h. Mostly invasive).
Thursday August 4
Past 24 hours
- Running on empty target (60 nA). Everything is going nicely and smoothly: 16.6h of ABU (69% efficiency).
Shift Reports
Reports
Issues
- temporary main trigger rate increase seems to be due to a hot FCal channel.
- Hot channel in FCAL
- FMWPC Chamber 1 hot wire and trips due to high current
- 2 ns shift fixed by Sean, follow-up by Justin
- A peak at wire number 40 for FMWPC Occupancy Layer 1 appears to be causing trips, see also [Early Riser shift summary https://logbooks.jlab.org/entry/4024097]
Plans
- Production running on empty target until Thursday
- Thursday morning, TAC run starting ~9am? (7-8 hours, assuming stable beam)
- RF Recovery for 4hrs on Friday to prepare for weekend. Starts at 7:15am.
- Monday day: 5 -> 4 pass change for Hall C (Around 4h. Mostly invasive).