Difference between revisions of "April 22, 2022 Tech group SAD meeting"
From GlueXWiki
(Created page with "= Meeting Time and Place == Friday April 22 2022 10:30am Hall D Counting House and Teams == Agenda == * Safety - * Hall D SAD Tasks Media:SAD2022_Acc_schedule.pdf ** CPP...") |
(→Agenda) |
||
Line 9: | Line 9: | ||
*** Microscope move/Hodoscope - poly shieldingcomplete [[image:hodo7.png|thumb]] | *** Microscope move/Hodoscope - poly shieldingcomplete [[image:hodo7.png|thumb]] | ||
*** Moveable Lead absorber - Tim to Write procedure | *** Moveable Lead absorber - Tim to Write procedure | ||
− | *** Target - Bobby - fit check - need drawings | + | *** Target - Bobby - fit check - need drawings [[image:Target-cartridge-lead.png|thumb]] |
*** Gas - Scot | *** Gas - Scot | ||
*** Helium bag [[image:He_bag.jpg|thumb]] | *** Helium bag [[image:He_bag.jpg|thumb]] | ||
Line 25: | Line 25: | ||
* FCAL Insert Drawings | * FCAL Insert Drawings | ||
* New Profiler install | * New Profiler install | ||
− | * New 3x3 CCAL for TAC [[Media:CPP_TAC.pdf]] | + | * New 3x3 CCAL for TAC [[Media:CPP_TAC.pdf]][[image:TAC-3x3.png|thumb]] |
* Tagger Radiator Mod [[Media:Fork_mod.pdf]] | * Tagger Radiator Mod [[Media:Fork_mod.pdf]] | ||
* Controls | * Controls |
Revision as of 09:19, 22 April 2022
Meeting Time and Place =
Friday April 22 2022 10:30am Hall D Counting House and Teams
Agenda
- Safety -
- Hall D SAD Tasks Media:SAD2022_Acc_schedule.pdf
- CPP INstall O:\halld_engineering\Installation Schedules
- Microscope move/Hodoscope - poly shieldingcomplete
- Moveable Lead absorber - Tim to Write procedure
- Target - Bobby - fit check - need drawings
- Gas - Scot
- Helium bag
- PS Parasitic Detectors stages
- FCAL Insert Module fabrication
- 40 brass straps per week needed
- matching mu metal to steel shields
- cutting tool
- Tagger NMR repair - Scot
- Tagger controls UPS
- BCAL Coldshot Chiller commissioning - Josh
- Target/Goni Turbo repair - Keith
- TEDF move in May to EEL stockroom area
- CPP INstall O:\halld_engineering\Installation Schedules
- JT file creation - Anthony gave presentation - file and instructions on O drive
- FCAL Insert Drawings
- New Profiler install
- New 3x3 CCAL for TAC Media:CPP_TAC.pdf
- Tagger Radiator Mod Media:Fork_mod.pdf
- Controls
- Solenoid vacuum controls
- General Maintenance
- On Call - Scot
- ePAS Training and trial https://www.jlab.org/esh/epas
Action Items
- Set up next PS parasitic meeting
- Decide on Goni maintenance
- Delineate ePAS permit requests for Isolation Certificate