Difference between revisions of "December 3, 2020 CPP Design Meeting"
From GlueXWiki
(Created page with "== Meeting Time and Place == Thursday Dec 03, 2020, 2pm Bluejeans https://bluejeans.com/465620466 * Present - Elton, Dave, Stephanie, Ilya, Rory, Mark S == Agenda == * Readi...") |
(→Minutes and Action Items) |
||
(4 intermediate revisions by the same user not shown) | |||
Line 7: | Line 7: | ||
== Agenda == | == Agenda == | ||
* Readiness Review | * Readiness Review | ||
− | * Schedule [[ | + | * Schedule [[Media:CPP_Schedule.pdf]] |
* Design/Procurement status | * Design/Procurement status | ||
* Things to work out | * Things to work out | ||
** Gas line manifold | ** Gas line manifold | ||
− | |||
− | |||
** Complete structural analysis | ** Complete structural analysis | ||
** Develop Detailed installation plan | ** Develop Detailed installation plan | ||
Line 19: | Line 17: | ||
== Minutes and Action Items == | == Minutes and Action Items == | ||
− | * | + | * Request for ERR submitted |
+ | * We need to show that everything is in place for a successful experiment | ||
+ | ** Design status | ||
+ | ** Procurement schedule/status | ||
+ | ** Installation schedule | ||
+ | *** For installing prior to 2022 run - full detector then uninstall a portion to run Primex | ||
+ | *** For Installing in middle of 2022 run | ||
+ | ** Installation procedure | ||
+ | ** Manpower availability | ||
+ | ** Calibration and Analysis procedures | ||
+ | ** Need Safety documents | ||
+ | ** OSP | ||
+ | ** Installation procedure/HDlist | ||
+ | ** EESAD | ||
+ | ** COO | ||
+ | |||
+ | * Will use CDC Gas system and crates | ||
+ | * Signal cables needed | ||
+ | * Elton to write OSP | ||
+ | * Elton to start ERR web page (use DIRC as an example) | ||
+ | * Tim to update install schedule to show 2 scenarios | ||
+ | * Tim to Start installation plan | ||
+ | * Rory to get wire chambers working | ||
+ | * Tim and Stephanie to complete support stand drawing package |
Latest revision as of 16:11, 7 December 2020
Meeting Time and Place
Thursday Dec 03, 2020, 2pm Bluejeans https://bluejeans.com/465620466
- Present - Elton, Dave, Stephanie, Ilya, Rory, Mark S
Agenda
- Readiness Review
- Schedule Media:CPP_Schedule.pdf
- Design/Procurement status
- Things to work out
- Gas line manifold
- Complete structural analysis
- Develop Detailed installation plan
- Develop Design/operational/Maintenance Requirements
Minutes and Action Items
- Request for ERR submitted
- We need to show that everything is in place for a successful experiment
- Design status
- Procurement schedule/status
- Installation schedule
- For installing prior to 2022 run - full detector then uninstall a portion to run Primex
- For Installing in middle of 2022 run
- Installation procedure
- Manpower availability
- Calibration and Analysis procedures
- Need Safety documents
- OSP
- Installation procedure/HDlist
- EESAD
- COO
- Will use CDC Gas system and crates
- Signal cables needed
- Elton to write OSP
- Elton to start ERR web page (use DIRC as an example)
- Tim to update install schedule to show 2 scenarios
- Tim to Start installation plan
- Rory to get wire chambers working
- Tim and Stephanie to complete support stand drawing package