Difference between revisions of "July 9, 2024 KLONG KPT post Review Design Meeting"
From GlueXWiki
(→Minutes/Actions) |
(→Minutes/Actions) |
||
Line 13: | Line 13: | ||
== Minutes/Actions == | == Minutes/Actions == | ||
− | * | + | * Plan for removing (decommission) KPT is to use Airpad casters that we procure for the CPS install |
+ | ** Will need to mend path between concrete and steel at cave entrance (sheet metal will do) | ||
+ | * Need to extend rails to be able to move KPT assy north when going back to GlueX | ||
+ | * Concern with radiation on 10" Kapton window - can replace with aluminum (maybe 0.5mm thk) (Tim to look at this) | ||
+ | * Need to move items upstream to make room for Profiler and new Active collimator | ||
+ | ** KPT assy move a few inches downstream | ||
+ | ** 2nd concrete wall moved 6" downstream to make allyway 34" wide (hopefully confined space permit not needed) | ||
+ | ** Permanent magnet moved 6" downstream (beampipe through wall will need to be installed before magnet) | ||
+ | ** Profiler needs to be moved as far from beamline as possible and shielded when not in use | ||
+ | * Discussed cooling/Power failure | ||
+ | ** Use temperature trip for beam "FSD" | ||
+ | ** Still need to write FMEA before ERR next year | ||
+ | * Need to have RADCON approve designs before ERR | ||
+ | * 98.5% beryllium ok for target | ||
+ | * 95% tungsten ok for absorber | ||
+ | * Keith to send out updated layout in a few days from the meeting | ||
+ | * Once layout is deemed good, we can start procuring items - we have about $100K to spend this fiscal year | ||
== Action Items == | == Action Items == |
Revision as of 15:02, 11 July 2024
Meeting Time and Place
Tuesday July 9, 2024, 1:30pm
- Invited - Hovanes Egiyan, Stephanie Worthington, Keith Harding, Igor Strakovsky, Tim Whitlatch, Vitaly Baturin, Eugene Chudakov, Josh Ballard, Amaryan Moskov
Agenda
- Review minutes from last meeting https://halldweb.jlab.org/wiki/index.php/January_18,_2024_KLONG_KPT_post_Review_Design_Meeting
- Discuss changes made as a result of the review last fall to prepare for procurements
- link to KLF wiki https://wiki.jlab.org/klproject/index.php/Main_Page
Minutes/Actions
- Plan for removing (decommission) KPT is to use Airpad casters that we procure for the CPS install
- Will need to mend path between concrete and steel at cave entrance (sheet metal will do)
- Need to extend rails to be able to move KPT assy north when going back to GlueX
- Concern with radiation on 10" Kapton window - can replace with aluminum (maybe 0.5mm thk) (Tim to look at this)
- Need to move items upstream to make room for Profiler and new Active collimator
- KPT assy move a few inches downstream
- 2nd concrete wall moved 6" downstream to make allyway 34" wide (hopefully confined space permit not needed)
- Permanent magnet moved 6" downstream (beampipe through wall will need to be installed before magnet)
- Profiler needs to be moved as far from beamline as possible and shielded when not in use
- Discussed cooling/Power failure
- Use temperature trip for beam "FSD"
- Still need to write FMEA before ERR next year
- Need to have RADCON approve designs before ERR
- 98.5% beryllium ok for target
- 95% tungsten ok for absorber
- Keith to send out updated layout in a few days from the meeting
- Once layout is deemed good, we can start procuring items - we have about $100K to spend this fiscal year