Difference between revisions of "July 9, 2024 KLONG KPT post Review Design Meeting"

From GlueXWiki
Jump to: navigation, search
(Meeting Time and Place)
(Minutes/Actions)
Line 13: Line 13:
 
== Minutes/Actions ==
 
== Minutes/Actions ==
  
* Tungsten absorber changed from 15.2 cm square to 14.2 cm  square
+
*
* Is existing 10" Kapton window adequate for KLONG radiation dosage? (Igor/Tim)
+
** Kapton is good for 6x10^9 RADS
+
* Is there enough space for a profiler and active collimator?
+
** Assume current AC and new profiler
+
** Bring AC and profiler 3D models into existing KPT model (Keith)
+
* Need to flip the location of the KPT assy to move north upon reinstall of GlueX (Keith)
+
* Need to address thermal fatigue of tungsten and beryllium by June (Tim)
+
* The review recommended an FMEA be performed for system failures such as cooling and power (Tim)
+
* Need to develop a plan for decommissioning and design but not procure the needed items (Tim)
+
* Make sure the tungsten composition is defined properly in power deposition and thermal models (Tim/Vitaly
+
* Hall A had some experience with tungsten heating
+
* We need to make sure RADCON approves the current design (Hovanes)
+
* Need to reissue overall layout for review (Keith)
+
  
 
== Action Items ==
 
== Action Items ==

Revision as of 10:17, 9 July 2024

Meeting Time and Place

Tuesday July 9, 2024, 1:30pm

  • Invited - Hovanes Egiyan, Stephanie Worthington, Keith Harding, Igor Strakovsky, Tim Whitlatch, Vitaly Baturin, Eugene Chudakov, Josh Ballard, Amaryan Moskov

Agenda

Minutes/Actions

Action Items