September 21, 2022 FCAL Insert Installation Meeting

From GlueXWiki
Revision as of 16:14, 20 September 2022 by Whitey (Talk | contribs) (Minutes)

Jump to: navigation, search

Meeting Time and Place

Wednesday September 21,2022 10am At Jefferson Lab, Hall D Counting House and on Teams

Agenda

Step assy.jpeg
Manifold assy.jpeg
Blocks.jpeg
DS platform.jpeg
FCAL upper cable trays.jpeg
FCAL BL Lower cabletrays.jpeg
FCAL BR Lower cabletrays.jpeg

Minutes

Action Items

  • Make a virtual 3D Mock up of baseline (Tim and Stephanie)
    • Assume HV and LV cables come from top and bottom
    • Assume signal cables are rg174 and patch in from downstream wall
    • Assume signal cables come along center pipe and fan out to crystals
    • Get samples of wires from Chris S. to use for model
  • Develop an lead-glass module unstacking plan (Sasha)
    • Criteria for category of repairs
    • # of bins
    • repair plan
  • Get quote on RG174 cables and connectors (Chris S.)
  • Come up with cable mapping plan (Fernando)