== Meeting Time and Place ==
 
== Meeting Time and Place ==
  
Wednesday September 07,2022 10am
+
Wednesday September 21,2022 10am
 
At Jefferson Lab, Hall D Counting House and on Teams
 
At Jefferson Lab, Hall D Counting House and on Teams
  
 
== Agenda ==
 
== Agenda ==
 
* Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/September_07,_2022_FCAL_Insert_Installation_Meeting
 
* Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/September_07,_2022_FCAL_Insert_Installation_Meeting
* Discuss Lead Glass and crystal module removal/install - Sasha
+
* [https://halldweb.jlab.org/detectors/fcal2/installation/module_install_9_21_22.pptx Discuss Lead Glass and crystal module removal/install] - Sasha
 
* Crystal signal cable concept - Stephanie
 
* Crystal signal cable concept - Stephanie
 
* Cable mapping requirements - Fernando
 
* Cable mapping requirements - Fernando
Line 13: Line 13:
 
* Assembly in ESB
 
* Assembly in ESB
 
*  [[Media:FCAL2_strawman_schedule.pdf]]
 
*  [[Media:FCAL2_strawman_schedule.pdf]]
*[[image:step_assy.jpeg|thumb]]
+
[[image:step_assy.jpeg|thumb]]
*[[image:manifold_assy.jpeg|thumb]]
+
[[image:manifold_assy.jpeg|thumb]]
*[[image:blocks.jpeg|thumb]]
+
[[image:blocks.jpeg|thumb]]
 +
[[image:DS_platform.jpeg|thumb]]
 +
[[image:FCAL_upper_cable_trays.jpeg|thumb]]
 +
[[image:FCAL_BL_Lower_cabletrays.jpeg|thumb]]
 +
[[image:FCAL_BR_Lower_cabletrays.jpeg|thumb]]
  
 
== Minutes ==
 
== Minutes ==
* I showed the strawman schedule and then how to handle the lead glass modules. The discussion then went right into cabling, which was discussed for the duration.
+
* Sasha presented an outline of his plan for lead-glass module removal, sorting and repairing.
* Sasha brought up the need for categorizing the existing modules before unstacking and then keep them separate.
+
** Sasha suggested it would be easier to sort and handle modules if we remove all the racks
** Sasha to write a plan on how to categorize and repair the modules
+
** Chris S. and Fernando prefer not to remove the racks on the platform
*** determine existing problems
+
** Arshak suggested erecting a platform upstream of the FCAL platform to facilitate handling
*** inspect as removed and decide which bin to go into
+
** Plan included 5 categories, good modules, color of module glass, pmt replace, base replace, repair wrap.
*** determine number of bins
+
** Malte suggested using existing bar codes to categorize, up front work needed to set up spreadsheet (Jinventory)
*** those with no issues, keep whole
+
* More discussions on cables
** Crates can handle around 1500 lbs
+
** Fernando plans on using 400 existing signal cables from modules
** should modules be removed from upstream or downstream?
+
** Eugene suggested maybe get new cables if we have to abandon in place
** Develop space plan based on Sasha'a plan (Tim)
+
** Malte reminded us that some of the existing cables may be brittle and need retermination if removed from crates.
* Cable discussion
+
** Still need new cable map to help with final decision of whether to remove all cables completely or just the detector end.
** How many new cable trays do we need (depends on plan)
+
** Stephanie showed layout for patch panel on downstream wall of dark room for signal cables. Cables inside would be thin cables attached to beam pipe at center and spread out to crystals
** 1600 new HV cables (through side wall patch panels)
+
** Signal cable config generally accepted and we will plan on this
** 1600 new LV cables (through side wall patch panels) - ribbon cable daisy chained on inside?
+
** May need chains with larger links or additional chain downstrean in Z of existing.
** 1200 or 1600 new signal cables depending if we reuse existing 400 cables
+
** Need tube with larger diameter (maybe 3") for photons to cleanly pass
** Do we remove all cables completely or just on detector end?
+
** Mark S. suggested using a cable manager below beamline to carry cables in Z
*** If only on one end?
+
* It was suggested that the additional cable weights may be too much for the existing dark room
****  the loose cables need to be supported and stowed somehow
+
* Need to discuss new crystal monitoring system and installation
**** little space left for work on platform
+
**** Less work for cabling folks
+
**** How to remove 400 existing signal cables
+
*** Remove cables completely?
+
**** Can remove racks so there is room to work on the platform
+
**** More work for cable folks
+
** How to route and support additional cables?
+
*** Bring HV and LV cables from patch panel on side walls
+
**** Route them from top and bottom to center
+
*** Add additional chain in Z to handle additional cables
+
*** Use smaller diameter (RGA 174 (2.8mm diam.)) for signal cables?
+
**** Route through patch panel or connector from DS wall
+
**** bring along center pipe and fan out?
+
**** need to decide on connectors and length
+
  
 
== Action Items ==
 
== Action Items ==
* Make a virtual 3D Mock up of baseline (Tim and Stephanie)
+
* Continue to add detail to module removal/repair plan (Sasha)
** Assume HV and LV cables come from top and bottom
+
* Determine cable mapping of new installation to help with cable decisions (Sasha)
** Assume signal cables are rg174 and patch in from downstream wall
+
* Get quote on 16" rg 174 cable with limos an barrel. (Chris S)
** Assume signal cables come along center pipe and fan out to crystals
+
* Check to see if existing dark room can handle additional cable load (Tim)
** Get samples of wires from Chris S. to use for model
+
* Look at installing a platform or scaffolding upstream of FCAL (Tim/Stephanie)
* Develop an lead-glass module unstacking plan (Sasha)
+
** Criteria for category of repairs
+
** # of bins
+
** repair plan
+
* Get quote on RG174 cables and connectors (Chris S.)
+
* Come up with cable mapping plan (Fernando)
+

Latest revision as of 12:48, 27 September 2022

Meeting Time and Place

Wednesday September 21,2022 10am At Jefferson Lab, Hall D Counting House and on Teams

Agenda

Step assy.jpeg
Manifold assy.jpeg
Blocks.jpeg
DS platform.jpeg
FCAL upper cable trays.jpeg
FCAL BL Lower cabletrays.jpeg
FCAL BR Lower cabletrays.jpeg

Minutes

  • Sasha presented an outline of his plan for lead-glass module removal, sorting and repairing.
    • Sasha suggested it would be easier to sort and handle modules if we remove all the racks
    • Chris S. and Fernando prefer not to remove the racks on the platform
    • Arshak suggested erecting a platform upstream of the FCAL platform to facilitate handling
    • Plan included 5 categories, good modules, color of module glass, pmt replace, base replace, repair wrap.
    • Malte suggested using existing bar codes to categorize, up front work needed to set up spreadsheet (Jinventory)
  • More discussions on cables
    • Fernando plans on using 400 existing signal cables from modules
    • Eugene suggested maybe get new cables if we have to abandon in place
    • Malte reminded us that some of the existing cables may be brittle and need retermination if removed from crates.
    • Still need new cable map to help with final decision of whether to remove all cables completely or just the detector end.
    • Stephanie showed layout for patch panel on downstream wall of dark room for signal cables. Cables inside would be thin cables attached to beam pipe at center and spread out to crystals
    • Signal cable config generally accepted and we will plan on this
    • May need chains with larger links or additional chain downstrean in Z of existing.
    • Need tube with larger diameter (maybe 3") for photons to cleanly pass
    • Mark S. suggested using a cable manager below beamline to carry cables in Z
  • It was suggested that the additional cable weights may be too much for the existing dark room
  • Need to discuss new crystal monitoring system and installation

Action Items

  • Continue to add detail to module removal/repair plan (Sasha)
  • Determine cable mapping of new installation to help with cable decisions (Sasha)
  • Get quote on 16" rg 174 cable with limos an barrel. (Chris S)
  • Check to see if existing dark room can handle additional cable load (Tim)
  • Look at installing a platform or scaffolding upstream of FCAL (Tim/Stephanie)