Line 27: | Line 27: | ||
** 1200 or 1600 new signal cables depending if we reuse existing 400 cables | ** 1200 or 1600 new signal cables depending if we reuse existing 400 cables | ||
** Do we remove all cables completely or just on detector end? | ** Do we remove all cables completely or just on detector end? | ||
− | *** If only on one end | + | *** If only on one end? |
**** the loose cables need to be supported and stowed somehow | **** the loose cables need to be supported and stowed somehow | ||
**** little space left for work on platform | **** little space left for work on platform | ||
**** Less work for cabling folks | **** Less work for cabling folks | ||
**** How to remove 400 existing signal cables | **** How to remove 400 existing signal cables | ||
+ | *** Remove cables completely? | ||
+ | **** Can remove racks so there is room to work on the platform | ||
+ | **** More work for cable folks | ||
+ | ** How to route and support additional cables? | ||
+ | *** Bring HV and LV cables from patch panel on side walls | ||
+ | **** Route them from top and bottom to center | ||
+ | *** Add additional chain in Z to handle additional cables | ||
+ | *** Use smaller diameter (RGA 174 or 179) for signal cables | ||
+ | **** Route through patch panel or connector from DS wall | ||
+ | **** bring along center pipe and fan out? |
Revision as of 14:50, 7 September 2022
Meeting Time and Place
Wednesday September 07,2022 10am At Jefferson Lab, Hall D Counting House and on Teams
Agenda
- Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/August_10,_2022_FCAL_Insert_Installation_Meeting
- Discuss Schedule, space, manpower and equipment needs
Minutes
- I showed the strawman schedule and then how to handle the lead glass modules. The discussion then went right into cabling, which was discussed for the duration.
- Sasha brought up the need for categorizing the existing modules before unstacking and then keep them separate.
- Sasha to write a plan on how to categorize and repair the modules
- determine existing problems
- inspect as removed and decide which bin to go into
- determine number of bins
- those with no issues, keep whole
- Crates can handle around 1500 lbs
- should modules be removed from upstream or downstream?
- Develop space plan based on Sasha'a plan (Tim)
- Sasha to write a plan on how to categorize and repair the modules
- Cable discussion
- How many new cable trays do we need (depends on plan)
- 1600 new HV cables (through side wall patch panels)
- 1600 new LV cables (through side wall patch panels) - ribbon cable daisy chained on inside?
- 1200 or 1600 new signal cables depending if we reuse existing 400 cables
- Do we remove all cables completely or just on detector end?
- If only on one end?
- the loose cables need to be supported and stowed somehow
- little space left for work on platform
- Less work for cabling folks
- How to remove 400 existing signal cables
- Remove cables completely?
- Can remove racks so there is room to work on the platform
- More work for cable folks
- If only on one end?
- How to route and support additional cables?
- Bring HV and LV cables from patch panel on side walls
- Route them from top and bottom to center
- Add additional chain in Z to handle additional cables
- Use smaller diameter (RGA 174 or 179) for signal cables
- Route through patch panel or connector from DS wall
- bring along center pipe and fan out?
- Bring HV and LV cables from patch panel on side walls