Difference between revisions of "September 07, 2022 FCAL Insert Installation Meeting"
From GlueXWiki
(→Agenda) |
(→Minutes) |
||
Line 11: | Line 11: | ||
== Minutes == | == Minutes == | ||
+ | * I showed the strawman schedule and then how to handle the lead glass modules. The discussion then went right into cabling, which was discussed for the duration. | ||
+ | * Sasha brought up the need for categorizing the existing modules before unstacking and then keep them separate. | ||
+ | ** Sasha to write a plan on how to categorize and repair the modules | ||
+ | *** determine existing problems | ||
+ | *** inspect as removed and decide which bin to go into | ||
+ | *** determine number of bins | ||
+ | *** those with no issues, keep whole | ||
+ | ** Crates can handle around 1500 lbs | ||
+ | ** should modules be removed from upstream or downstream? | ||
+ | ** Develop space plan based on Sasha'a plan (Tim) | ||
+ | * Cable discussion | ||
+ | ** How many new cable trays do we need (depends on plan) | ||
+ | ** 1600 new HV cables (through side wall patch panels) | ||
+ | ** 1600 new LV cables (through side wall patch panels) - ribbon cable daisy chained on inside? | ||
+ | ** Do we remove all cables completely or just on detector end? | ||
+ | *** If only on one end, | ||
+ | **** the loose cables need to be |
Revision as of 14:31, 7 September 2022
Meeting Time and Place
Wednesday September 07,2022 10am At Jefferson Lab, Hall D Counting House and on Teams
Agenda
- Minutes from last meeting https://halldweb.jlab.org/wiki/index.php/August_10,_2022_FCAL_Insert_Installation_Meeting
- Discuss Schedule, space, manpower and equipment needs
Minutes
- I showed the strawman schedule and then how to handle the lead glass modules. The discussion then went right into cabling, which was discussed for the duration.
- Sasha brought up the need for categorizing the existing modules before unstacking and then keep them separate.
- Sasha to write a plan on how to categorize and repair the modules
- determine existing problems
- inspect as removed and decide which bin to go into
- determine number of bins
- those with no issues, keep whole
- Crates can handle around 1500 lbs
- should modules be removed from upstream or downstream?
- Develop space plan based on Sasha'a plan (Tim)
- Sasha to write a plan on how to categorize and repair the modules
- Cable discussion
- How many new cable trays do we need (depends on plan)
- 1600 new HV cables (through side wall patch panels)
- 1600 new LV cables (through side wall patch panels) - ribbon cable daisy chained on inside?
- Do we remove all cables completely or just on detector end?
- If only on one end,
- the loose cables need to be
- If only on one end,