(Tuesday, September 14)
Line 11: Line 11:
 
## Sometimes single 16 ch fADCs report 0.   
 
## Sometimes single 16 ch fADCs report 0.   
 
## Sometimes CSS on gluon02 doesn't show the same thing as CSS on gluon03.
 
## Sometimes CSS on gluon02 doesn't show the same thing as CSS on gluon03.
 +
# Run plan
 +
#* Wait for beam delivery.  Begin experiment commissioning. [https://halldweb.jlab.org/primexd/run_plan/Run_Plan_Fall_2021.pdf Run plan]
 +
 +
=Wednesday, September 15=
 +
# Last 24 hours:
 +
#*
 +
# Report/issue
 +
#* We still need an RC for September 29 to October 6
 +
#*
 
# Run plan
 
# Run plan
 
#* Wait for beam delivery.  Begin experiment commissioning. [https://halldweb.jlab.org/primexd/run_plan/Run_Plan_Fall_2021.pdf Run plan]
 
#* Wait for beam delivery.  Begin experiment commissioning. [https://halldweb.jlab.org/primexd/run_plan/Run_Plan_Fall_2021.pdf Run plan]

Revision as of 09:53, 14 September 2021

<- Back to Run Coordination Meetings:Summer2021

Tuesday, September 14

  1. Last 24 hours:
  2. Report/issue
    1. rocfcal11 cannot be remotely rebooted
    2. Sometimes whole crates are missing from CSS view.
    3. Sometimes single 16 ch fADCs report 0.
    4. Sometimes CSS on gluon02 doesn't show the same thing as CSS on gluon03.
  3. Run plan
    • Wait for beam delivery. Begin experiment commissioning. Run plan

Wednesday, September 15

  1. Last 24 hours:
  2. Report/issue
    • We still need an RC for September 29 to October 6
  3. Run plan
    • Wait for beam delivery. Begin experiment commissioning. Run plan