Line 3: Line 3:
 
=Monday 01 November=
 
=Monday 01 November=
 
#Over the weekend:
 
#Over the weekend:
#* Recorded 331M events from Fri, 8am till target was emptied. Then XXM events with empty target until now
+
#* Recorded 331M events from Fri, 8am till target was emptied. Then 1400M+ events with empty target until now
 
#* Comment box on DAQ machine did not show up -> restarting DAQ brought it back. Missing comments for some runs recorded in logbook [https://logbooks.jlab.org/entry/3934452]
 
#* Comment box on DAQ machine did not show up -> restarting DAQ brought it back. Missing comments for some runs recorded in logbook [https://logbooks.jlab.org/entry/3934452]
 
#* [https://logbooks.jlab.org/entry/3934565 Follow-up Re: Follow-up Re: TAGH scalers, roctagh2]
 
#* [https://logbooks.jlab.org/entry/3934565 Follow-up Re: Follow-up Re: TAGH scalers, roctagh2]
Line 11: Line 11:
 
#* Over the weekend, reference plots have been updated to reflect status with empty target [https://logbooks.jlab.org/entry/3935037]
 
#* Over the weekend, reference plots have been updated to reflect status with empty target [https://logbooks.jlab.org/entry/3935037]
 
#* When we run with empty target, dont run AI for CDC HV. Stay with 2125V fixed value [https://logbooks.jlab.org/entry/3935003]
 
#* When we run with empty target, dont run AI for CDC HV. Stay with 2125V fixed value [https://logbooks.jlab.org/entry/3935003]
 +
#* [https://logbooks.jlab.org/entry/3935332 power cycle of rocTAGH1, rocTAGH2, restart DAQ] due to frozen TAGH scalers
 +
#* Spooky halloween shift - accelerator became unstable (lots of RF trips) sunday night [https://logbooks.jlab.org/entry/3935421]
 
#Issues:
 
#Issues:
#* BCAL noise at 10 o'clock
+
#* <s>BCAL noise at 10 o'clock</s>
 
#* Bleedthrough
 
#* Bleedthrough
 
# [https://halldweb.jlab.org/primexd/run_plan/Run_Plan_Fall_2021.pdf Plan:]
 
# [https://halldweb.jlab.org/primexd/run_plan/Run_Plan_Fall_2021.pdf Plan:]
 
#* Continue production at 200nA with the solenoid on.
 
#* Continue production at 200nA with the solenoid on.
 
#* Since Hall A cannot run at present, we are the priority hall.  
 
#* Since Hall A cannot run at present, we are the priority hall.  
#* Maintenance day on Wed 11/03
+
#* Maintenance day on Wed 11/03 '''beam will be shut off at ~6am'''
#* Beam energy change planned for 11/05-11/07; decision pending due to availability of Hall A
+
#** Hall D will go into controlled access for maintenance work (FCAL, ...?)
 +
#* Beam energy change planned for 11/05-11/07
 +
#* Hall A scheduled to come back online on Monday, 11/08
 
=Friday 29 October=
 
=Friday 29 October=
 
#Last 24h:
 
#Last 24h:

Revision as of 08:19, 1 November 2021

MCC whiteboard Meeting Bluejeans 660743227

Monday 01 November

  1. Over the weekend:
  2. Issues:
    • BCAL noise at 10 o'clock
    • Bleedthrough
  3. Plan:
    • Continue production at 200nA with the solenoid on.
    • Since Hall A cannot run at present, we are the priority hall.
    • Maintenance day on Wed 11/03 beam will be shut off at ~6am
      • Hall D will go into controlled access for maintenance work (FCAL, ...?)
    • Beam energy change planned for 11/05-11/07
    • Hall A scheduled to come back online on Monday, 11/08

Friday 29 October

  1. Last 24h:
    • Recorded 1090M+ events
    • Change out of C02
    • RadCon replaced light bulb (was really broken) in our rapid access beacon with an LED bulb
      • Access was necessary, but machine was actually down during that time
    • RCDB web interface was unreachable, shift crew contacted administrator and the service was restarted
    • HallC BCM calibration should not have affected us, but they use varying beam currents for that procedure, which may have changed bleedthrough during run 81620 (see [6])
    • New wiki page with short-term guidance for shifters [7]
    • Beam - RF Timing differences with different trigger types
    • RAID beeping in DAQ room
  2. Issues:
    • BCAL noise at 10 o'clock
    • Bleedthrough
  3. Plan:
    • Continue production at 200nA with the solenoid on.
    • Since Hall A cannot run at present, we are the priority hall.
    • Maintenance day shifted to Wed 11/03
    • Beam energy change planned for 11/05-11/07; decision pending due to availability of Hall A

Thursday 28 October

  1. Last 24h:
  2. Issues:
  3. Plan:
    • Continue production at 200nA with the solenoid on.
    • Since Hall A cannot run at present, we are the priority hall.
    • Hall C BCM calibration moved to today (Thursday) 2:30pm.
    • Maintenance day planned for Tue 11/02
    • Beam energy change planned for 11/05-11/07; decision pending due to availability of Hall A