[https://cebaf.jlab.org/files/ops/accboard/ MCC whiteboard]
 
[https://cebaf.jlab.org/files/ops/accboard/ MCC whiteboard]
[https://bluejeans.com/660743227 Meeting Bluejeans 660743227]  
+
[https://bluejeans.com/660743227 Meeting Bluejeans 660743227]
=Thursday 28 October=
+
=Wednesday November 03=
 
#Last 24h:
 
#Last 24h:
 +
#* Recorded 1029M+ events with full LHe4 target
 +
#* [https://logbooks.jlab.org/entry/3936040 U1-9-TOP reboot]
 +
#* [https://logbooks.jlab.org/entry/3936068 runai on gluon47 hangs]
 +
#* Some repeated trouble with RootSpy [https://logbooks.jlab.org/entry/3936227] and DAQ comments box [https://logbooks.jlab.org/entry/3936204]
 +
#Issues:
 +
#* Bleedthrough
 +
# [https://halldweb.jlab.org/primexd/run_plan/Run_Plan_Fall_2021.pdf Plan:]
 +
#* '''TODAY: Maintenance day'''
 +
#* Continue production at 200nA with the solenoid on after that.
 +
#* MCC (Jay) discussed possibility to move up the energy shift to Thu, swing
 +
#** Controlled access planned for maintenance work (e.g. FCAL [https://logbooks.jlab.org/entry/3935581])
 +
#* Beam energy change planned for 11/05-11/07
 +
#** RadCon survey for friday morning is requested
 +
#* Next RC will be Alex Austregesilo
 +
=Tuesday November 02=
 +
#Last 24h:
 +
#* Recorded 83M events with empty target, one run in raw-mode, then 726M+ events with full LHe4 target
 +
#* gluonraid1 was degraded -> one disk was replaced (RAID5, no hot spare; rebuild started automatically)
 +
#* [https://logbooks.jlab.org/entry/3935583 ADC-TDC Timing Shift in TAGH]
 +
#* [https://logbooks.jlab.org/entry/3935590 BCAL ADC-TDC Timing Shifts]
 +
#* [https://logbooks.jlab.org/entry/3935599 Thermocouple locations]
 +
#* [https://logbooks.jlab.org/entry/3935642 NMR signal and tagger rates]
 +
#* Day shift crew updated RootSpy reference plots for full target run [https://logbooks.jlab.org/entry/3935704]
 +
#* CDC Voltages IOC lost communication, rebooted [https://logbooks.jlab.org/entry/3935781]
 +
#Issues:
 +
#* Bleedthrough
 +
# [https://halldweb.jlab.org/primexd/run_plan/Run_Plan_Fall_2021.pdf Plan:]
 +
#* Continue production at 200nA with the solenoid on.
 +
#* Since Hall A cannot run at present, we are the priority hall.
 +
#* '''Maintenance day tomorrow, Wed 11/03'''
 +
#** Controlled access planned for maintenance work (e.g. FCAL [https://logbooks.jlab.org/entry/3935581])
 +
#* Beam energy change planned for 11/05-11/07
 +
=Monday November 01=
 +
#Over the weekend:
 +
#* Recorded 331M events from Fri, 8am till target was emptied. Then 1400M+ events with empty target until now
 +
#* Comment box on DAQ machine did not show up -> restarting DAQ brought it back. Missing comments for some runs recorded in logbook [https://logbooks.jlab.org/entry/3934452]
 +
#* [https://logbooks.jlab.org/entry/3934565 Follow-up Re: Follow-up Re: TAGH scalers, roctagh2]
 +
#* Target was emptied at 6:10pm Firday [https://logbooks.jlab.org/entry/3934588]
 +
#* [https://logbooks.jlab.org/entry/3934591 BCAL noise at 10 o'clock]
 +
#* [https://logbooks.jlab.org/entry/3934854 Note on neutron background in Hall D]
 +
#* Over the weekend, reference plots have been updated to reflect status with empty target [https://logbooks.jlab.org/entry/3935037]
 +
#* When we run with empty target, dont run AI for CDC HV. Stay with 2125V fixed value [https://logbooks.jlab.org/entry/3935003]
 +
#* [https://logbooks.jlab.org/entry/3935332 power cycle of rocTAGH1, rocTAGH2, restart DAQ] due to frozen TAGH scalers
 +
#* Spooky halloween shift - accelerator became unstable (lots of RF trips) sunday night [https://logbooks.jlab.org/entry/3935421]
 +
#* Target will be filled this morning (after the meeting). Chris C requested short access during filling to watch target interlock panel
 +
#Issues:
 +
#* <s>BCAL noise at 10 o'clock</s>
 +
#* Bleedthrough
 +
# [https://halldweb.jlab.org/primexd/run_plan/Run_Plan_Fall_2021.pdf Plan:]
 +
#* Continue production at 200nA with the solenoid on.
 +
#* Since Hall A cannot run at present, we are the priority hall.
 +
#* Maintenance day on Wed 11/03 '''beam will be shut off at ~6am'''
 +
#** Hall D will go into controlled access for maintenance work (FCAL, ...?)
 +
#* Beam energy change planned for 11/05-11/07
 +
#* Hall A scheduled to come back online on Monday, 11/08
 +
=Friday October 29=
 +
#Last 24h:
 +
#* Recorded 1090M+ events
 +
#* [https://logbooks.jlab.org/entry/3933753 Change out of C02]
 +
#* RadCon replaced light bulb (was really broken) in our rapid access beacon with an LED bulb
 +
#** Access was necessary, but machine was actually down during that time
 +
#* RCDB web interface was unreachable, shift crew contacted administrator and the service was restarted
 +
#* HallC BCM calibration should not have affected us, but they use varying beam currents for that procedure, which may have changed bleedthrough during run 81620 (see [https://logbooks.jlab.org/entry/3933796])
 +
#* New wiki page with short-term guidance for shifters [https://halldweb.jlab.org/hdops/wiki/index.php/Short_Term_Run_Plan]
 +
#* [https://logbooks.jlab.org/entry/3934095 Beam - RF Timing differences with different trigger types]
 +
#* [https://logbooks.jlab.org/entry/3934271 RAID beeping in DAQ room]
 +
#Issues:
 +
#* BCAL noise at 10 o'clock
 +
#* Bleedthrough
 +
# [https://halldweb.jlab.org/primexd/run_plan/Run_Plan_Fall_2021.pdf Plan:]
 +
#* Continue production at 200nA with the solenoid on.
 +
#* Since Hall A cannot run at present, we are the priority hall.
 +
#* Maintenance day '''shifted to Wed 11/03'''
 +
#* Beam energy change planned for 11/05-11/07; decision pending due to availability of Hall A
 +
=Thursday October 28=
 +
#Last 24h:
 +
#* Recorded 949M+ events
 
#* [https://logbooks.jlab.org/entry/3933197 Emergency Control box intermittent alarms ]
 
#* [https://logbooks.jlab.org/entry/3933197 Emergency Control box intermittent alarms ]
 
#* [https://logbooks.jlab.org/entry/3933263 TAGH scalers froze (roctagh2)]; TAGH1 and TAGH2 crates power cycled
 
#* [https://logbooks.jlab.org/entry/3933263 TAGH scalers froze (roctagh2)]; TAGH1 and TAGH2 crates power cycled
 
#* Some issues with starting root spy ([https://logbooks.jlab.org/entry/3933234 see day shift summary])
 
#* Some issues with starting root spy ([https://logbooks.jlab.org/entry/3933234 see day shift summary])
#* [https://cebaf.jlab.org/dtm/open-events?event_id=12451 XXhrs Downtime due to issue with magnet shunt module]
+
#* 2.5hrs downtime due to issue with magnet shunt module (has been replaced)
#** Chris C (target) requested access to check heater power supply of the condenser.
+
#** Chris C (target) requested access to check heater power supply of the condenser [https://logbooks.jlab.org/entry/3933441].
 
#** Our rapid access beacon is not working again ([https://logbooks.jlab.org/entry/3933422 turning, but no light!])
 
#** Our rapid access beacon is not working again ([https://logbooks.jlab.org/entry/3933422 turning, but no light!])
 
#** RadCon escorted Chris in and out of the hall.
 
#** RadCon escorted Chris in and out of the hall.
 +
#* [https://logbooks.jlab.org/entry/3933655 Rebinning issue in compton monitoring macro]
 
#Issues:
 
#Issues:
#* Get rapid access beacon fixed
+
#* Rapid access beacon gives no light. The same failure happened 2 weeks ago, light bulb was replaced [https://logbooks.jlab.org/entry/3924326]
 
#* Low energy tagger counters?
 
#* Low energy tagger counters?
 
#* BCAL noise at 10 o'clock
 
#* BCAL noise at 10 o'clock
Line 20: Line 98:
 
#* Since Hall A cannot run at present, we are the priority hall.  
 
#* Since Hall A cannot run at present, we are the priority hall.  
 
#* Hall C BCM calibration moved to today (Thursday) 2:30pm.
 
#* Hall C BCM calibration moved to today (Thursday) 2:30pm.
 +
#* Maintenance day planned for Tue 11/02
 +
#* Beam energy change planned for 11/05-11/07; decision pending due to availability of Hall A

Latest revision as of 08:23, 3 November 2021

MCC whiteboard Meeting Bluejeans 660743227

Wednesday November 03

  1. Last 24h:
  2. Issues:
    • Bleedthrough
  3. Plan:
    • TODAY: Maintenance day
    • Continue production at 200nA with the solenoid on after that.
    • MCC (Jay) discussed possibility to move up the energy shift to Thu, swing
      • Controlled access planned for maintenance work (e.g. FCAL [3])
    • Beam energy change planned for 11/05-11/07
      • RadCon survey for friday morning is requested
    • Next RC will be Alex Austregesilo

Tuesday November 02

  1. Last 24h:
  2. Issues:
    • Bleedthrough
  3. Plan:
    • Continue production at 200nA with the solenoid on.
    • Since Hall A cannot run at present, we are the priority hall.
    • Maintenance day tomorrow, Wed 11/03
      • Controlled access planned for maintenance work (e.g. FCAL [6])
    • Beam energy change planned for 11/05-11/07

Monday November 01

  1. Over the weekend:
    • Recorded 331M events from Fri, 8am till target was emptied. Then 1400M+ events with empty target until now
    • Comment box on DAQ machine did not show up -> restarting DAQ brought it back. Missing comments for some runs recorded in logbook [7]
    • Follow-up Re: Follow-up Re: TAGH scalers, roctagh2
    • Target was emptied at 6:10pm Firday [8]
    • BCAL noise at 10 o'clock
    • Note on neutron background in Hall D
    • Over the weekend, reference plots have been updated to reflect status with empty target [9]
    • When we run with empty target, dont run AI for CDC HV. Stay with 2125V fixed value [10]
    • power cycle of rocTAGH1, rocTAGH2, restart DAQ due to frozen TAGH scalers
    • Spooky halloween shift - accelerator became unstable (lots of RF trips) sunday night [11]
    • Target will be filled this morning (after the meeting). Chris C requested short access during filling to watch target interlock panel
  2. Issues:
    • BCAL noise at 10 o'clock
    • Bleedthrough
  3. Plan:
    • Continue production at 200nA with the solenoid on.
    • Since Hall A cannot run at present, we are the priority hall.
    • Maintenance day on Wed 11/03 beam will be shut off at ~6am
      • Hall D will go into controlled access for maintenance work (FCAL, ...?)
    • Beam energy change planned for 11/05-11/07
    • Hall A scheduled to come back online on Monday, 11/08

Friday October 29

  1. Last 24h:
    • Recorded 1090M+ events
    • Change out of C02
    • RadCon replaced light bulb (was really broken) in our rapid access beacon with an LED bulb
      • Access was necessary, but machine was actually down during that time
    • RCDB web interface was unreachable, shift crew contacted administrator and the service was restarted
    • HallC BCM calibration should not have affected us, but they use varying beam currents for that procedure, which may have changed bleedthrough during run 81620 (see [12])
    • New wiki page with short-term guidance for shifters [13]
    • Beam - RF Timing differences with different trigger types
    • RAID beeping in DAQ room
  2. Issues:
    • BCAL noise at 10 o'clock
    • Bleedthrough
  3. Plan:
    • Continue production at 200nA with the solenoid on.
    • Since Hall A cannot run at present, we are the priority hall.
    • Maintenance day shifted to Wed 11/03
    • Beam energy change planned for 11/05-11/07; decision pending due to availability of Hall A

Thursday October 28

  1. Last 24h:
  2. Issues:
  3. Plan:
    • Continue production at 200nA with the solenoid on.
    • Since Hall A cannot run at present, we are the priority hall.
    • Hall C BCM calibration moved to today (Thursday) 2:30pm.
    • Maintenance day planned for Tue 11/02
    • Beam energy change planned for 11/05-11/07; decision pending due to availability of Hall A