Difference between revisions of "Run Planning Meeting Notes, June 16 - June 22, 2022"

From GlueXWiki
Jump to: navigation, search
Line 21: Line 21:
 
#*[https://logbooks.jlab.org/entry/4005504 2 FCAL bases changed]
 
#*[https://logbooks.jlab.org/entry/4005504 2 FCAL bases changed]
 
#*[https://logbooks.jlab.org/entry/4005509 Tagger HV crate replaced] to hopefully solve issues with 24 tagger channel causing problems.
 
#*[https://logbooks.jlab.org/entry/4005509 Tagger HV crate replaced] to hopefully solve issues with 24 tagger channel causing problems.
 +
#*F1 TDC replaced in tagger. It is version 33 of firmware while all the rest are version 32.  This is not a problem, ver 33 has 2 more diagnostic registers (these could be useful if there are event building issues one day but we can just update then if so.)  Apparently has not solved DAQ live time issue.
 
#*[https://logbooks.jlab.org/entry/4005586 Helicity signal added to DAQ]
 
#*[https://logbooks.jlab.org/entry/4005586 Helicity signal added to DAQ]
 
#*[https://logbooks.jlab.org/entry/4005626 PERP issues were due to corrupted goniometer setting] Hovanes Fixed
 
#*[https://logbooks.jlab.org/entry/4005626 PERP issues were due to corrupted goniometer setting] Hovanes Fixed
 
#*[https://logbooks.jlab.org/entry/4005635 Ion chambers adjusted]  Neutron radiation levels in the Tagger Hall by coincidence were confounding.
 
#*[https://logbooks.jlab.org/entry/4005635 Ion chambers adjusted]  Neutron radiation levels in the Tagger Hall by coincidence were confounding.
#*[https://logbooks.jlab.org/entry/4005729 PERP orientation spectrum looked terrible.] Resolved with electron beam tuning. Edge not as stable as PARA (shift crew anecdotal).
+
#*[https://logbooks.jlab.org/entry/4005729 PERP orientation spectrum looked terrible.] Resolved with electron beam tuning. Apparently issue was caused by running Hall D oprbit locks without Hall D beam present, leading to the beam walking off.
 
#*[https://logbooks.jlab.org/entry/4005683 U1-10-TOP MPOD crate has problems leading to LV issues on ST and PS.]
 
#*[https://logbooks.jlab.org/entry/4005683 U1-10-TOP MPOD crate has problems leading to LV issues on ST and PS.]
 
#*TAC or Trigger work  
 
#*TAC or Trigger work  
Line 32: Line 33:
 
#*[https://logbooks.jlab.org/entry/4005383 Beam energy monitoring.]
 
#*[https://logbooks.jlab.org/entry/4005383 Beam energy monitoring.]
 
#Issues
 
#Issues
#*[https://logbooks.jlab.org/entry/4005315 CTOF FP trigger timing change in wrong direction]
+
#* Tagger NMR
#*24 tagger channels off.  Tagger access tuesday to look at this.
+
#* DIRC sensor
 +
#* DAQ livetime
 +
#* Beam position stability
 +
#* U1-10-TOP MPOD crate
 
#Plans
 
#Plans
 
#*AC locks parameter tuning
 
#*AC locks parameter tuning

Revision as of 08:01, 22 June 2022

↑ Back to Run Coordination Meetings:Summer2022

Meeting are via ZoomGov: connect (Meeting ID: 160 199 0060 / Passcode 8394)

MCC whiteboard

Hall D counting room white board

Spreadsheet with list of runs


Wednesday June 22

  1. Last 24h:
  2. Shift Summaries
  3. Reports
  4. Issues
    • Tagger NMR
    • DIRC sensor
    • DAQ livetime
    • Beam position stability
    • U1-10-TOP MPOD crate
  5. Plans
    • AC locks parameter tuning
    • PS and TAGH HV scans
    • Accelerator maintenance day Thursday
  6. Commissioning steps temporarily postponed:
    • Flux optimization/Act .Col. calibration
    • Bleed-through test: measure bleed-through with A slit as usual and A slit completely closed to see whether using B slit would help.


Tuesday June 21

  1. Last 24h:
  2. Reports
  3. Issues
  4. Plans
    • RF recovery Tuesday and machine tuning for Hall C high current.
      • Change F1TDCs in Tagger that may be causing live time issues.
      • Install helicity fibers in Tagger
      • Change HV crate in tagger that is causing issues.
    • Accelerator maintenance day Thursday
  5. Commissioning steps temporarily postponed:
    • Flux optimization/Act .Col. calibration
    • PS and TAGH HV scans
    • Bleed-through test: measure bleed-through with A slit as usual and A slit completely closed to see whether using B slit would help.


Monday June 20

  1. Last 24h:
  2. Reports
  3. Issues
    • Beam position is unstable
    • DAQ live time fluctuations. [4] Tagger access tuesday to look at this.
    • 24 tagger channels off. Tagger access tuesday to look at this.
  4. Plans
    • RF recovery Tuesday and machine tuning for Hall C high current.
      • Change F1TDCs in Tagger that may be causing live time issues.
      • Install helicity fibers in Tagger
      • Change HV crate in tagger that is causing issues.
    • Accelerator maintenance day Thursday
  5. Commissioning steps temporarily postponed:
    • Flux optimization/Act .Col. calibration
    • PS and TAGH HV scans
    • Bleed-through test: measure bleed-through with A slit as usual and A slit completely closed to see whether using B slit would help.


Sunday June 19

  1. Last 24h:
  2. Reports
  3. Issues
  4. Plans
    • Flux optimization/Act .Col. calibration
    • RF recovery Tuesday
    • Accelerator maintenance day Thursday
  5. Commissioning steps temporarily postponed:
    • PS and TAGH HV scans
    • Bleed-through test: measure bleed-through with A slit as usual and A slit completely closed to see whether using B slit would help.

Saturday June 18

  1. Last 24h:
  2. Reports
    • From PD-RC 8:45 meeting.
      • Generally everyone is somewhat unhappy. :-(
    • CPP dEdx issues. CDC is likely fine. Its gain and hit efficiency (hits found/hits measured) are normal. But tracking is missing the start counter, & the target isn't in the usual spot.
  3. Issues
    • 24 tagger channels off.
  4. Plans
    • Flux optimization/Act .Col. calibration
    • Trigger development for TOF trigger
    • RF recovery Tuesday
    • Accelerator maintenance day Thursday
  5. Commissioning steps temporarily postponed:
    • PS and TAGH HV scans
    • Bleed-through test: measure bleed-through with A slit as usual and A slit completely closed to see whether using B slit would help.


Friday June 17

  1. Last 24h:
    • Tagger voltage alarms
    • Beam returned at 11 pm.
    • Harp scans performed [7][8][9]
    • Beam envelope looks good Accelerator have asked us to put these projections in the elog in future.
    • No CH edge observed. Hovanes helped to get diamond aligned overnight. [10]
    • Ran quasi production for NPP. Pressure change CDC alarm twice.
  2. Reports
    • From PD-RC 7:45 meeting.
      • Hall C not getting high current, more work is needed
      • Hall B will need a spin dance
    • Low rates in TOF [11] and low current in CDC [12]
    • Spreadsheet with list of runs
  3. Issues
    • 24 tagger channels off
  4. Plans
    • Flux optimization/Act .Col. calibration
    • Trigger development for TOF trigger
    • RF recovery Tuesday
    • Accelerator maintenance day Thursday
  5. Commissioning steps temporarily postponed:
    • PS and TAGH HV scans
    • Bleed-through test: measure bleed-through with A slit as usual and A slit completely closed to see whether using B slit would help.

Thursday June 16

  1. Last 24h:
    • No beam since last meeting
    • Still getting tagger voltage alarms (should we just turn those counters off?)
  2. Reports
  3. Issues
    • High trigger rate in CTOF
      • MWPC #6 window cover removed. If successful, great. Otherwise, attempt to move helium bag downstream.
  4. Plans:
  5. Upcoming Items:
    • PS and TAGH HV scans
    • Bleed-through test: measure bleed-through with A slit as usual and A slit completely closed to see whether using B slit would help.
    • Tagger Access:
      • Change HV crate (Nick, Chris)
      • Install helicity fibers and connect to DAQ